1 / 12

CXC Manager’s Status Report

CXC Manager’s Status Report. Chandra User Committee Meeting Roger J. Brissenden 25 June 2002. Program Level Status. Spacecraft continues to perform superbly and operations continue to be routine. No significant spacecraft hardware problems or safe modes have occurred since last report.

harlan
Download Presentation

CXC Manager’s Status Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CXC Manager’s Status Report Chandra User Committee Meeting Roger J. Brissenden 25 June 2002

  2. Program Level Status • Spacecraft continues to perform superbly and operations continue to be routine. No significant spacecraft hardware problems or safe modes have occurred since last report. • Flight software patch to mitigate EPHIN hardware failure flag glitch running SCS 107. • 827 Cycle 4 proposals (817 GO, 10 GTO) submitted by deadline of 3/15/02. Peer Review held on schedule June 18-20. • Plan agreed to with MSFC and HQ on adding resources in the Ed/Outreach area to provide additional emphasis on SSUs. • CXC Quarterly review 4/23/02. No major actions resulted from the review. MSFC Independent Annual Review to be held 9/5/02. • Contract change in work to direct SAO to perform call for proposals in place of NRA – similar to HST model. • CXC Contract extension proposal for 11-months from 9/30/02 to 8/31/03 in final sign-off with MSFC. • MSFC is pursuing a JOFOC approach for contract post 8/31/03. Second 5-year budget level briefing given to HQ as part of POP-02. • No significant near-team budget or staffing issues. Out-year profile in work with HQ. CXC Status Report/CUC

  3. Items from January 02 CUC • “Occasionally a few datasets are delivered well beyond the mean lag of 7 days. We suggest that each OBSID has a built-in alarm so that the appropriate scientists are informed when an OBSID has been unduly delayed.” The archive group has installed a script which checks the automated processing (AP) status for observations which have been in the queue for a week or more. The duty scientist is notified of all such observations. In addition DS has implemented monthly manual checks of the AP status tables for observations which have been received but for which processing has not completed. • “We recommend that more channels be opened by which either the Director or the CXC Outreach office can learn of potentially interesting results. Possibilities include charging CUC members to take some responsibility for identifying potentially appropriate science results and sensitizing PIs of successful large proposals of this issue.” The CXC has reached agreement on a plan with MSFC and HQ to increase the resources in the Education and Public Outreach area. An important task for the new resources will be to address this issue. CXC Status Report/CUC

  4. Operations • Nominal Spring 2002 eclipse season. • Patch up-linked to increase glitch counters and mitigate EPHIN hardware failure glitch counter trips of SCS 107 (second occurrence on 4/2/02 however EPHIN hardware is nominal and cause traced to subtle timing condition). • Successful test of bright earth constraint limitation. Expected to lead to reduction of the 20 degree constraint yielding more flexible scheduling. • 6 executions of SCS 107 due to high solar activity, 1 assessed as due to EPHIN hardware failure glitch. • No ACIS CTI degradation above expectations. • Anomalies • None. • Hosted a number of visits or discussions with other mission teams: • NGST, SIRTF, Kepler, SIM, HST (July). CXC Status Report/CUC

  5. Operations • Load interrupt TOOs Date Target Request 3/3/02 NGC 4388 1 day 3/11/02 RX J170930.2-2639 3 days 3/12/02 SN2002B0 3 days 3/28/02 GRB020321 3 days 4/5/02 GRB020405 1 day 4/5/02 XTE J1751-305 3 day 5/10/02 XTE J0929-314 3 days 6/3/02 GRB020531 3 day • Operations Ground System Updates Date Version Change 2/27/02 ONLS 3.8.2 New front end processor file interface 5/2/02 OFLS 9.2B Major update of momentum management 5/2/02 GRETA 1.2.2 Plot bug fix 6/12/02 OFLS 9.3 Interface to AGASC 1.5 (starcat update) CXC Status Report/CUC

  6. MUPS Fuel Usage CXC Status Report/CUC

  7. MUPS Warm Start Count CXC Status Report/CUC

  8. Scheduled Observing Efficiency CXC Status Report/CUC

  9. Cumulative Observations for NRA-3 CXC Status Report/CUC

  10. Data Systems • Data processing • Average time from observation to data delivery has been maintained at approximately a week • Data System Software Releases (major) Date Release Content includes 2/6/02 DS 6.6 NRA4 Budget software WebChaSeR fixes, MTA alerts 3/22/02 DS 6.7 New SUN cc compiler SI mode, data base and HRC processing updates 6/14/02 DS 6.8 Solaris 8 port of data system. CXC Status Report/CUC

  11. Data Delivery Effectiveness CXC Status Report/CUC

  12. Chandra Grant Awards CXC Status Report/CUC

More Related