1 / 12

ECCS5209 Project Planning & Control

Faculty of Applied Engineering and Urban Planning. Civil Engineering Department. 2 nd Semester 2010/2011. ECCS5209 Project Planning & Control. Example. Eng: Ismail Zakaria Al Daoor. Project Crashing. Time-Cost Trade-Off ( Project Crashing ). Example

harry
Download Presentation

ECCS5209 Project Planning & Control

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Faculty of Applied Engineering and Urban Planning Civil Engineering Department 2nd Semester 2010/2011 ECCS5209 Project Planning & Control Example Eng: Ismail Zakaria Al Daoor

  2. Project Crashing

  3. Time-Cost Trade-Off ( Project Crashing ) Example The durations and direct costs for each activity in the network of a small construction contract under both normal and crash conditions are given in the following table. Establish the least cost for expediting the contract. Determine the optimum duration of the contract assuming the indirect cost is LE 125/day.

  4. 20 12 D(23) 24 12 0 12 12 20 20 25 27 47 59 47 A(0) B(8) E(5) G(20) I(12) 0 12 14 22 22 27 27 47 47 59 2@100 2@150 1@50 5@60 2@75 12 27 27 32 32 45 C(15) F(5) H(13) 12 27 29 34 34 47 3@200 1@300 2@40 Act. N.D C.D ∆.D C.C. N.C ∆.C Slop A 12 10 2 7200 7000 200 100 B 8 6 2 5300 5000 300 150 C 15 12 3 4600 4000 600 200 D 23 23 0 5000 5000 0 0 E 5 4 1 1050 1000 50 50 F 5 4 1 3300 3000 300 300 CPM = A-C-G-I G 20 15 5 6300 6000 300 60 H 13 11 2 2850 2500 350 175 I 12 10 2 3150 3000 150 75

  5. Time-Cost Trade-Off ( Project Crashing ) 1. The activity on the critical path with the lowest cost slope is G, this activity can be crashed by 5 days, but if it is crashed by more than 2 days another critical path will be generated. Therefore, activity G will be crashed by 2 days only. Then adjust timing of the activities. A new critical path will be formed, A-C-F-H-I. New contract duration is 57 days. The cost increase is 2 x 60 = LE 120.

  6. Time-Cost Trade-Off ( Project Crashing ) 2. At this step the activities that can be crashed are listed below: Either A at cost LE 100/day Or C at cost LE 200/day Or I at cost LE 75/day Or F & G at cost LE 360/day Or H & G at cost LE 100/ day Activity I is chosen because it has the least cost slope, and it can be crashed by 2 days. Because this is last activity in the network, it has no effect on other activities. New contract duration is 55 days. The cost increase is 2 x 75 = LE 150. Cumulative cost increase = 120 + 150 = LE 270

  7. Time-Cost Trade-Off ( Project Crashing ) 3. Now, we could select A or both H & G, because they have the same cost slope. Activity A is chosen to be crashed. This will change the timings for all activities, but no new critical path will be formed. New contract duration is 53 days. The cost increase is 2 x 100 = LE 200. Cumulative cost increase = 270 + 200 = LE 470

  8. Time-Cost Trade-Off ( Project Crashing ) 4. Now, activities H & G can be crashed by 2 days each. A new critical path A-B-D-I will be formed. New contract duration is 51 days. The cost increase is 2 x 100 = LE 200. Cumulative cost increase = 470 + 200 = LE 670

  9. Time-Cost Trade-Off ( Project Crashing ) 5. At this stage, the network have three critical paths. The activities that can be crashed are listed below: Either C & B at cost LE 350/day Or F, G & B at cost LE 510/day Activities C & B are chosen because they have the least cost slope. New contract duration is 49 days. The cost increase is 2 x 350 = LE 700. Cumulative cost increase = 670 + 700 = LE 1370 Now, there is no further shortening is possible.

  10. Time-Cost Trade-Off ( Project Crashing ) The contract duration and the corresponding cost are given in the table below.

  11. Time-Cost Trade-Off ( Project Crashing )

  12. Question

More Related