THEMIS Electric Field Instrument (EFI) Mission CDR The THEMIS EFI Team. Outline. Personnel and Organization Summary of EFI Status at MCDR Requirements, Specifications, and Design Compliance Requirements Top-Level Design Error Budgets Status of Subsystem Design, Fabrication, and Testing
E N D
THEMIS Electric Field Instrument (EFI) • Mission CDR • The THEMIS EFI Team
Outline • Personnel and Organization • Summary of EFI Status at MCDR • Requirements, Specifications, and Design Compliance • Requirements • Top-Level Design • Error Budgets • Status of Subsystem Design, Fabrication, and Testing • Fabrication, Integration, and Test • Schedule: Henry Ford Help Us… • Operations Planning • Deploy and Commisioning • Etc.
Personnel and Organization • Organizational Chart (all UCB unless noted): • Prof. F. Mozer (EFI Co-I). • Drs. J. Bonnell, G. Delory, A. Hull (Project Scientists) • P. Turin (Lead ME), Dr. D. Pankow (Advising ME) • B. Donakowski (EFI Lead ME, SPB, Facilities) • G. Dalton (SPB, EFI GSE ME), K. McKee (ME), S. Martin (MT) • R. Duck (AXB ME) • D. Schickele (Preamp, Sensor Cables, Facilities ME) • S. Grimmer, R. Gupta (ME GSRs) • S. Jelinsky, S. Marker (Facilities and TVAC Staff) • S. Harris (BEB Lead EE), H. Richard (BEB EE) • J. Lewis, F. Harvey (GSE) • Technical Staff (H. Bersch, Y. Irwin, H. Yuan, B. Dalen, N. Castillo) Wm. Greer (UCLA), et al.) • R. Ergun (DFB Co-I; CU-Boulder) • J. Westfall, A. Nammari, K. Stevens (DFB SysE, EEs; CU-Boulder) • C. Cully (DFB GSR; CU-Boulder)
EFI Status at I-CDR • Requirements and Design: • The current EFI design meets Mission and Instrument requirements. • The design is complete. • One new requirement (CG positioning) has been imposed post-PDR. • Procurement: • All long-lead items have been procured in sufficient quantities to allow for ETU and initial FLT production: • EEE parts ordered; rad testing of required parts complete. • SPB and AXB mechanical items (custom wire cable, stacers, actuators, motors) are in-house, or on order with expected delivery on schedule for FLT build up. • FLT machining on order, with expected 25% fulfilment (1-1/2 SC of parts) by early July, and remainder by end of July. • Personnel: • Team is complete: • All design engineering positions filled. • One FT MT position filled Mar ’04; 0ne PT MT positions filled internally by personnel transitioning over from STEREO; two ME GSRs hired for summer and fall to support FLT production startup. • Assembly and Test: • ETUs of all major elements have been assembled and partially or largely tested. • Testing will be completed by July 2004.
RFA and Design Trade Closure • RFAs from I-PDR, M-PDR, and I-CDR all responded to a/o closed out: • ESC Spec is on Rev. D1; includes detailed specs on the requirement and methods to achieve it; ESC roster developed in Feb ’04, allowing close collaboration between Swales and UCB on problem areas and mitigation techniques. • EMI Spec completed Mar ’04. • Detailed Instrument I&T plan under development as part of ETU Testing; synthesized from Polar, Cluster, etc. • Mechanical (INST-RFA 13, 14, 15, 19, 20, R03), and Electrical (INST-RFA 16AB, 17) arising from ICDR, as well as Internal Mechanical Review. • Open Design Trades from PDR closed out: • Boom lengths set at 50/40/7.67 meters tip-to-tip based on CBE of Probe mass properties and std. GSFC and UCB dynamic stability requirements and boom mode resonance keep-outs. • Ti-N chosen over DAG-213 for SPB sensor coating. • Heritage brushed motor chosen for SPB deploy. • Braid biasing selected, and Distal Braid length set at 3 m. • DAC implementation on BEB chosen (ADC5544), and bias offset range of +/- 40 V maintained. • EFI filters on DFB chosen to be Bessel-type.
EFI Block Diagram • A High-Input Impedance Low-Noise Voltmeter in Space sheath sensor preamp Floating ground generation BIAS USHER Bias channels GUARD VBraidCtrl VBraid BRAID Vref
Top-Level Design (1) • Diagram of THEMIS EFI Elements AXB Preamp Enclosure Preamp PWB BEB SPB DFB GSE
Top-Level Design (2) • Description of THEMIS EFI Elements • Three-axis E-field measurement, drawing on 30 years of mechanical and electrical design heritage at UCBSSL. • Closest living relatives are Cluster, Polar and FAST, with parts heritage from CRRES (mechanical systems, BEB designs, preamp designs).
Top-Level Design (3) • Description of THEMIS EFI Elements • Radial booms: • 22-m cable length (up to 50 m tip-to-tip deployed; SPB-X to be deployed to 50 m, SPB-Y to be deployed to 40 m). • 8-cm dia., Ti-N-coated spherical sensor. • 3-m, 0.009-inch dia. fine wire to preamp enclosure. • SMA-actuated door release mechanism. • Brushed motor design. • Significant volume and mass relief relative to closest living relatives. • USHER and GUARD bias surfaces integral to preamp enclosure. • BRAID bias surface of 3-m length inboard of preamp (common between all 4 radial booms). • Sensor is grounded through 10 Mohm resistance when stowed, providing ESD protection and allowing for internal DC and AC functional tests. • External test/safe plug (motor,door actuator,turns click, ACTEST) to allow for deploy testing/safeing and external signal injection.
Top-Level Design (4) • Description of THEMIS EFI Elements • Axial booms: • 2.8-m stacer with ~1-m DAG-213-coated whip stacer sensor. • New, fully-qualified Double DAD design based on FAST axial booms. • New, fully-qualified FrangiBolt deployment actuation. • Preamp mounted in-line, between stacer and sensor. • USHER and GUARD bias surfaces integral to preamp enclosure. • No BRAID bias surface. • Sensor is grounded through 7 Mohm resistance when stowed, providing ESD protection and allowing for internal DC and AC functional tests. • External test/safe plug (deploy actuator, ACTEST) to allow for deploy testing/safeing and external signal injection.
Top-Level Design (5) Description of THEMIS EFI Elements • BEB block diagram:
Top-Level Design (6) • Description of THEMIS EFI Elements • BEB Signal Processing and Control Specifications:
Top-Level Design (7) Description of THEMIS EFI Elements • DFB functional block diagram:
Top-Level Design (8) Description of THEMIS EFI Elements • DFB signal flow block diagram:
Top-Level Design (9) • Description of THEMIS EFI Elements • DFB Signal Processing and Control Requirements: • +/- 100 V analog input relative to AGND. • CMRR >= 80 dB on differential E-Field channels. • DC-coupled E-fields and sensor potential waveforms from 0-4 kHz. • AC-coupled E-fields from 0-6 kHz. • AC-coupled SCM (AC B-field) from 0-4 kHz. • Log(AKR POWER) from 100-500 kHz. • E-field and sensor potentials for on-board Spin Fit data processing. • Filter bank with df/f better than 25% from 8 Hz to 4 kHz. • On-board projection of E and dB into ExB/E.B coordinates for FFT processing (“Derived Quantities”). • On-board computation of FFT spectra (Standard and Derived Quantities).
Top-Level Design (10) • Performance Specification • Spacecraft potential: +/- 60 V, 1.8 mV resolution, better than 46 uV/m resolution (allows ground reconstruction of E from spacecraft potential to better than 0.1 mV/m resolution). • DC-coupled E-field: +/- 300 mV/m, 9 uV/m resolution, 0-4 kHz. • AC-coupled E-field: +/- 50 mV/m, 3.0 uV/m resolution, 0-6 kHz. • AKR log(Power) channel: 1 uV/m to 4.5 mV/m RMS amplitude, 400-kHz bandwidth, 100-500 kHz. • 16-bit resolution.
Top-Level Design (11) • Thermal Predicts: 60-min-long eclipse 180-min-long eclipse
Error Budgets • DC (ie. spin frequency or less): • Mechanical and Electrical design chosen to keep individual sources of systematic error on SPBs less than 1.0 mV/m: • CMRR of differential E-field channels >= 80 dB. • DC Gain within a few parts in 1000 of 1.0; better than 1% component matching then ensures CMRR >= 80 dB. • ESC requirements on potential uniformity and area of freely-charging exposed surfaces (eg. Insulators). • Different boom lengths (40 and 50 m) chosen to allow detection of systematic errors due to wake and boom shorting effects. • Fine wire length reduces shorting effect to 5% or less. • Improved Preamp Mechanical design reduces differential photocurrent collection by factor of 3-10 relative to Cluster-II (3 sufficient). • Increased requirement on CG placement accuracy to ensure alignment of boom pairs to better than 0.5 degrees (see detail, next slide). • AXB error budget more liberal, due to shorter length (errors scale as 1/L to 1/L3), and lack of Mission Requirement; few mV/m: • 4-cm control of +Z/-Z boom lengths to counteract shift of electrical center along spin axis (antenna mast vs. separation ring). • ESC requirements (AXB measurements will provide for a sensitive test of ESC compliance on-orbit).
CG Placement Requirement • CG Offset Effect on Systematic Error in Sunward E-Field: • Center-of-Gravity (CG) offset from center of SPB boom system drives angular offset between opposing fine wires. • Opposing fine wires go through sun-alignment at different spin phases, leading to systematic bipolar error signal. • Primary effect is on instantaneous sunward E-field component. • CG positioning Requirement of 1 part in 100 of SPB Cable pivot radius (approx. 4 mm, or 0.166 inch) drives magnitude of error below 0.8 mV/m, worst-case. (CG offset)/(pivot radius) 0.01 0.001
Error Budgets • EFI Spectral Coverage and System Noise Estimates Maximum Spectra (DC-Coupled) 1/f3 1/f flat CDI BBF AKR band 1-LSB Spectra (DC-Coupled) Preamp and Rbias Current Noise Preamp Voltage Noise axial radial 10-Hz Ac-coupled roll-in Spin frequency 4-kHz Anti-aliasing roll-off
Error Budgets • RE02 BB Limits set to give S/N of > 3 for expected AKR amplitudes. • RE02 NB limits set to drop equivalent BB spectral density below expected amplitudes below 4 kHz on SPB.
Error Budgets • 7.5 pF input capacitance of preamp has significant effect on gain above 100 Hz: • SPB AC gain is 0.65. • AXB AC gain is 0.45. • Rolloff frequency from DC to AC gain (resistive to capacitive coupling) is predominantly controlled by sheath resistance, which is under direct control via sensor bias current. • AC gain in both cases is still sufficient to achieve required measurements over desired frequency interval.
Assembly and Test To-Date • ETUs • AXB (1 unit): assembled March ’04; RT and TVAC deploy tested, March ’04; redesigned, rebuilt, redeployed April ’04; Sensor redesign, May ’04; Straightness, May ’04; Horiz. Deploy (length cal), June ’04. • SPB (1 unit): assembled April ’04; Housing, Door, and Door Actuator redesigned and rebuilt May ’04; vibe’d June ’04; TVAC and RT Deploy, June ’04. • Preamp Enclosure: Four ETUs built, April, ’04 and integrated into ETU Cables, SPB, and AXB; Cable termination redesigned, May ’04 (post-I-CDR); revised ETUs to be built June ’04. • Cables: One Prototype, two ETU Sensor Cables, and one special Thermal Cable fabricated March 29 – April 9, ’04; integrated with ETU Preamp PWBs and ETU SPB and AXB for vibe testing, and Preamp Thermal Model Simulator.
Assembly and Test To-Date • ETUs (con’t) • Preamp PWB: Two ETU Preamp PWB assembled April 9 ’04; integrated with ETU Preamp PWBs and ETU SPB and AXB for vibe testing. One Flight-like PWB assembled for Preamp Thermal Modeling (nominal operation at –130 C!). • BEB: One ETU built, Mar ’04; functional testing, Mar-Apr ’04, design qualified, meets required specifications; Integrated BEB-Preamp-Cable testing ongoing, June ’04. • DFB: One BB ETU with core FPGA functionality (CDI interpreter, waveform filters and filter banks) completed mid-May ’04; successfully integrated with BEB, DCB, and EFI/BEB EGSE, mid-May ’04; true ETU fab and assy late June-early July ’04.
Assembly and Test To-Date • GSE and Harnessing • EGSE: BEB/EFI Electrical GSE complete and characterized, April ’04; spare unit with reduced fuctionality to support BEB Flight Board Testing, on-order, June ’04. • Faraday Boxes: two Faraday boxes with internal fixtures and wiring (signal paths and Plasma Simulators), complete, June ’04. • MGSE: AXB TVAC fixtures done; AXB FrangiBolt simulator done; AXB HDeploy Track, TBC, June ’04; SPB TVAC Takeup Reels, TBC, June ’04 for SPB TVAC; SPB TVAC Fine Wire Deploy Reels, TBC, June ’04. • TVAC Harnessing: design complete, April-May ’04; SPB ETU built, May ’04; AXB to be built, July ’04. • ETU Harnessing: design complete, May ’04; under fabrication to support II&T, June ’04. • Misc. Test Harnessing: dual boom unit Y-Test Harness, built May ’04. Breakout boxes, etc., designed and built as needed.
Near-Term Testing • Mechanical • AXB and SPB Vibe (June 9 and 10) – units passed. • SPB TVAC (Deploy Testing) (June 18-25; pending completion of B20 “Bayside” refurbishment), AXB TVAC complete and successful. • AXB and SPB Deploy Calibrations (late June). • Testing required to support FLT machining orders complete. • Thermal • Long-Eclipse Thermal Simulation and Thermal Shock (aka. L-N2 Dunk) for Preamp, -130 C to 60 C (May 2004; July 2004) • Electrical • Integrated electrical testing of EFI and BEB (all of June 2004; EFI/BEB EGSE complete; Faraday Boxes complete in late April). • Formal Preamp Thermal Qualification (TVAC cycles and DPA) (Jul-Aug 2004, parallel with F1 FLT build). • Suite-Level Testing (II&T) • EFI ETU delivered to II&T July 2004.
Parts Procurement, Qual, and Contamination • Long-Lead Items • All long-lead items in-house or on schedule for delivery to support July ’04 start of Flight production. • Custom Cable • SPB Flight motors, bearings, slip rings, machine parts. • AXB Flight stacers, bearings. • Preamp Enclosure machine parts and Cable Fab fixtures. • BEB parts kits. • DFB parts kits. • Preamp parts kits. • Qualification Testing • All parts passed radiation (AD5544 DAC and LTC1604 ADC, in particular). • Formal qualification of Preamp OP-15 and design via TVAC and DPA in parallel to ETU and Initial Flight Build (July ’04). • Contamination • All suspect parts sent to UCLA for magnetic characterization (eg. SPB motors and geartrain).
Facilities • ETU Testing • Refurbished UCBSSL Silver B20 “Bayside” TVAC Chamber • Accommodates up to 4 SPB. • UCBSSL Addition High Bay “Geoffrey” TVAC Chamber • Accommodates fully-deployed AXB vertically. • Vibe Testing done off-site. • AXB Horizontal Deploy Track. • SPB Vertical Deploy Fixtures in High Bay • Alternately, Std. Horizontal Deploy in SSL “Dungeon”. • FLT Testing • Same facilities as ETU, plus: • New UCBSSL Silver B20 “EFI Snout” TVAC Chamber • Accommodates fully-deployed AXB horizontally. • Vibe testing done off-site.
Calibration and Test • Mechanical and Electro-Mechanical • SPB Deploy Length • Turns Count • Deploy Rate • SPB Door Actuation and Function • AXB Deploy Length • Repeatability • Stiffness and Straightness • SPB Door SMA and AXB Deploy FrangiBolt Currents • SPB and AXB Cable Continuity and Isolation during Deploy • Electrical • EFI/BEB Calibration • Quiescent and Operational Currents • DC Functional Tests (Gain, Offset, CMRR, Linearity, 0.1% Matching) • AC Functional Tests (Transfer Function, CMRR, Slew Rate, Linearity) • EFI/SCM/FGM via DFB Phase Intercalibration • See Suite-Level I&T.
Assembly and Test Flow SPB Assembly and Test Flow, based on ETU Experience:
Instrument (Suite) I&T Plan • Integration and Test • Instrument I&T takes place at UCBSSL. • Environmental (TVAC, Vibe, Suite EMC as per THM-SYS-005 Environmental Verification Spec). • Limited and Comprehensive Performance Testing: • SPB Motor Simulators (aka. Motor-in-a-Box) and AXB Test FrangiBolts (aka. FrangiBolt-in-a-Box) used for pre- and post-environmental functional tests of deploy mechanisms, as well as dummy electrical loads during “fake” TVAC deploy testing. • Internal DC and AC functional test capability used for pre- and post-environmental functional tests of sensors; sensors may be directly stimulated via ACTEST line on Test/Enable plug. • End-to-End SPB and AXB TVAC Deploy Testing (IDPU-controlled; Motor-in-a-Box and FrangiBolt-in-a-Box). • Integrated Fields System (DCB, DFB, EFI, SCM, FGM) modes testing: Nominal, Slow, Fast, Torturous Data Exchange, and “Mode X”. • Phase intercalibration between EFI, SCM, and FGM performed using EFI Test/Enable Plugs, SCM Mu-Metal Box, FGM TCU and 12-channel, 16-bit, +/- 10-V National Instruments DAC system.
S/C (Probe) I&T Plan • Integration and Test • Probe I&T takes place at Swales Aerospace. • Environmental (TVAC, Vibe, Shock, EMI; as per THM-SYS-005 Environmental Verification Spec). • Limited and Comprehensive Performance Testing: • Sensors via internal DC and AC Functional Test capability, monitored through ITOS. • Actuators via external Boom Loads Simulator (BLS) and Test/Enable plugs, monitored through ITOS. • Sensors may be stimulated externally via breakout on BLS, if required (non-standard test). • Initial ITOS requirements outlined, Apr 2004. • Red/Green tag items: • One red tag Snout Cover per SPB (4 total). • One red/green Test/Enable plug per SPB (4 total). • One red tag Tube Cover per AXB (2 total). • One red/green Test/Enable plug supporting both AXBs (1 total)
F1-F2 Production Schedule SPB Cables Vibe TVAC, RT Preamp 13 Sep ‘04 AXB 5 Jul ‘04 BEB Cals 4 Oct ‘04 26 Jul ‘04
FLT Production Schedule • Grassroots estimate, based on ETU experience (1 person-day/subassy, TVAC and RT testing experience, electrical checkout, etc.). • Subassembly Assy tasks (eg. SPB Motor, Spool, etc.) carry 100% margin. • Rate setting steps are Mechanical Test and BEB Board Test (3-week durations). • 3-week delivery cadence, with 2-week overlap between Fn Boom Assy and Fn+1 Subassembly Assy work. • 5-week delivery cadence removes all overlap between successive Boom and Subassembly Assy work. • Downstream schedule risk will be reduced by using Subassembly schedule margin and larger summer labor pool (F1) (GSRs) to lay in overstock for F2 through F6. • Dedicated TVAC personnel (Jelinsky, McKee, Marker) used to reduce schedule risk from spreading Engineering staff thinly between Assembly, Test, and I&T.
Deploy and Commissioning • Draft Deploy and Commissioning plan developed Nov 2003. • Draft plan refined Mar 2004 in response to revised launch date (21 Aug -> 21 Oct 2006). • EFI SOH to be determined on all probes using stowed DC and AC functional test capability during initial on-orbit check-out. • Instrument SOH used to determine probe assignment. • EFI deployed on all probes after placement in initial science orbits. • EFI deployed in 6 to 7 steps: • 5 to 6 intermediate deploy lengths with spin up for SPB. • 1 step to deploy both AXB. • Primary constraints on deploy and commissioning: • 1 30-minute TM contact per 3-1/2 hours (thermal). • Desire to gather science data at intermediate deploy lengths and in different plasma regimes.