160 likes | 461 Views
OmegaPS Analyzer. New Functionality in Release R4.4 OUGM 2013 Graham Brum. Major Functions Added. Scheduled Maintenance Tasks QTT at LOM1 and OnPE SRSF Months Per Year hierarchy XML Data Files Single Item Spares – Multi-Item Extended “Cost Per” Report Initial Buy Report.
E N D
OmegaPS Analyzer New Functionality in Release R4.4 OUGM 2013 Graham Brum
Major Functions Added Scheduled Maintenance Tasks QTT at LOM1 and OnPE SRSF Months Per Year hierarchy XML Data Files Single Item Spares – Multi-Item Extended “Cost Per” Report Initial Buy Report Slide
Scheduled Maintenance • Add task details for • Calendar based tasks • Operational Unit based tasks • Operational demands for Scheduled spares replacement Slide
SM R&O can be done at any LOM • On-PE tasks are used to “Inspect” the PE - CBM • Scheduled (Calendar) • Scheduled (Operational) • The LRU is R/R at On-PE when condition is met • The removed LRU can be sent to any LOM for repair, R&O Slide
Model for SM • Total SM Mean Hours per Month = MHRSM(Op) + MHRSM(Cal) • MHRSM(Op) = Tasks per Month * Mean Task Time ((TOHM(PE)/MTBSM(Op)) * DC * QinPE) * MTSM(Op) • MHRSM(Cal) = Monthly Hours PE * QPE (MTSM * PETPM* QinPE) * QPE PETPM based on MTBSM MB (e.g. Weeks = 4) Slide
Quantity of Techs Trained • assigned to: • LOM1, or • On PE at First Line sites • Uses Labour Rates as defined for each level Slide
SRSF • Site Reliability Stress Factor • Released in R4.3.2 • Allows for Reliability (MTBF) adjustment for: • a Part • at a Site • Multiplier adjustment to MTBF when demands are generated a that specified site for the associated part Slide
Select SRSF button Opens form Set SRSF to adjust MTBR for an item at a site Slide
Months Per Year Hierarchy • Months per year operating for PE is limited to only operating sites • Can be assigned at three levels: • Operating months for the PE • Operating months for the Site • Default value for all PE/Sites • Model uses the ‘best’ value from Default, Site, PE Slide
XML Transfer Files • Data Files: • costs; echelon; structure; stock; STE • Result Files: • results; labour; spares; log • Project Transfer File: • Every data element in the project • Used for transfers between Analyzer and OSAM models. Slide
Example Results.xml Results.xml viewed using XML Notepad 2007 from Microsoft Slide
Multi selection of Single Item Sparing runs Select one or many items to include Sort by clicking column headers Select method for Target Availability. Manual displays graph for each item Slide
Extended “cost-per” LCC reports • A cost breakdown report by Part in the configuration • Can select the ‘denominator’ • LCC • Per PE • Per Operating Unit • Per Failure • Others can be added in the future • Suggestions……? Slide
Future Development • ASOAR -> APAU -> DATM • Design Availability Target Model • MHLH -> ADES -> TLAS • Through Life Availability Simulation • LORA2 Linear Programming research • Extended Task Modelling • Business Case Analysis LCC/TLC Cost Breakdown Structures Slide