Wastewater Treatment & Collection System Improvements. Treatment Plant Improvements Replace aged infrastructure Increase hydraulic and organic capacity Provide new technology to address facility compliance challenges
E N D
Treatment Plant Improvements Replace aged infrastructure Increase hydraulic and organic capacity Provide new technology to address facility compliance challenges Provide ability to divert, hold and return influent flow during high flow events (precipitation, snow melt, etc.) Convert the WWTP from a seasonal discharger to a continuous discharge
Summary of Improvements New head works (screening/grit removal) Conversion of Lagoon #4 to excess flow basin Install new septage receiving station Install new Oxidation Ditch & refurbish existing Oxidation Ditch Provide two new final clarifiers Provide new ultraviolet disinfection system for plant discharge New final effluent cascade aeration New plant electrical system including new standby generator
Construction Status Estimated date of substantial completion – January 1, 2015 • Difficult winter construction period • Due to increased efforts this spring – back on estimated schedule • Challenging site access conditions (thank you to our neighbors)
Construction Progress • Electrical bank • New Oxidation Ditch • Two new clarifiers • Septage receiving building Pictures
Existing Oxidation Ditch – left foreground New Oxidation Ditch – Right foreground Two New Final Clarifiers - Background
Interim Operations Plan Period: June1 – August 31 • Both Oxidation Ditches – out of service (constructability) • WWTP will store influent in 3 existing lagoons • September 1 – existing oxidation ditch will return to service, resume active treatment of influent flow to plant • As influent flow volumes allow – redirect stored influent wastewater back through active oxidation ditch process
Interim Ops Plan Pro’s • Takes place during normal no discharge period • Expedites construction • Most efficient method of facility completion • Best available treatment season for lagoon activity • Working with non-domestic users to minimize discharge to WWTP Con’s • No mechanical facility treatment • Odor generating potential • Storage volume availability • Extended period to treat accumulated influent
Collection System Improvements • New main pump station (PS #16) – replaces PS #6 • Replace PS #4 with new PS #4 • Sewer rehabilitation
Wastewater Treatment & Collection System Improvements Questions/Comments