1 / 10

Romanens – CH – S3 – 0220

Impact of Distributed Generation on Grid Protection. Paper n° 0220. BKW FMB Energie AG Switzerland. Florian Romanens. Romanens – CH – S3 – 0220. Content. Introduction BKW FMB Energie AG and its grid Changes in existing distribution grids Some requirements considered by BKW

helga
Download Presentation

Romanens – CH – S3 – 0220

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Impact of Distributed Generation on Grid Protection Paper n° 0220 BKW FMB Energie AG Switzerland Florian Romanens Romanens – CH – S3 – 0220

  2. Content • Introduction • BKW FMB Energie AG and its grid • Changes in existing distribution grids • Some requirements considered by BKW • Protection concept • Short-circuits and earth-faults • Frequency • Conclusion

  3. Introduction • BKW FMB Energie AG and its grid • Swiss utility company based in Bern • Generation, transport and distribution of electricity • Grid: • Transmission grid: 380kV, 220kV • Over-regional distribution grid: 132kV, 50kV • Regional distribution grid: 16kV, 0.4kV Interconnected topology radial topology

  4. Introduction • Changes in existing distribution grids • Existing distribution grids are often built only for load flow • DG can create a change in the power flow by BKW: - 16kV - star point isolated

  5. Some requirements considered by BKW • DG-protection systems have to recognize: • earth-f. and short-c. in case of fault on the DG-side • quickly trip the DG-circuit breaker • earth-f. and short-c. in case of fault in the grid • normally allow sufficient time for the grid to clear the fault. If the fault is not cleared after a certain time, trip the DG-circuit breaker • over / under frequency and over / under voltage • have to stay connected if f>47.5Hz and U>80% • Normally, a communication between substation and DG is used • to realize an “intertrip” from the protection of the bay (in the substation) to the DG-circuit breaker

  6. Short-circuits and earth-faults • Protection zones • Each zone is defined by the CBs and CTs (beginning / end) • Paper n°0220 shows the protection concept for each zone 16kV switchgear Line between substation and DG DG-zone Other parts of the grid

  7. Short-circuits and earth-faults • Example: fault in the 16kV GIS in the substation • GIS have a rated arcing duration of 1.0s • Faults in the GIS have to be cleared within 1.0s On the BB: cleared by the reverse interlocking busbar prot. with special “BB-intertrip” Between CB and cable termination, the “intertrip” to the circuit breaker of the DG is used intertrip Simple over current functions are not appropriated

  8. Frequency • Example with the frequency • DG have to stay connected if f>47.5Hz & U>80% • Important for the stability of the grid in case of a large disturbance • Under Frequency Load Shedding (UFLS) • If the load is bigger than the generation, the frequency will fall. In this case, a certain amount of load has to be shed, but the production has to stay connected to support the grid. generation load

  9. Conclusion • DG are / will be connected to the distribution grid • Due to DG, the power flow-direction can change • Grid configuration has to take DG into account • Especially protection concept have to be adapted for DG • The sum of a lot of small generation units can impact on the stability and reliability of the grid • Some requirements mentioned are difficult to fulfill. Therefore, the collaboration among the partners involved in projects with DG is very important

  10. Thank you for you attention!

More Related