130 likes | 244 Views
ABT review on the LIU-PSB Systems. PSB KSW Magnets September 10 th 2014 L. Feliciano TE/ABT. Agenda. Introduction Planning Main project milestones Kick requirements Hardware Magnets Layout Issues Half magnets impregnation and ceramic chambers Budget Spending profile
E N D
ABT review on the LIU-PSB Systems PSB KSW Magnets September 10th 2014 L. Feliciano TE/ABT
Agenda • Introduction • Planning • Main project milestones • Kick requirements • Hardware • Magnets Layout • Issues • Half magnets impregnation and ceramic chambers • Budget • Spending profile • Conclusions L. Feliciano
Introduction • The painting bump is made by using a series of 4 horizontal kicker stacks (KSW), outside of the injection region to produce a closed orbit offset of 35 mm at the injection foil. • A few of the existing KSW magnets will need to be re-engineered and re-located. • The present layout configuration and the electrical parameters of the KSW Painting Magnets will significantly change. L. Feliciano
Planning • The original planning was made on the assumption that the magnets would be ready end 2014. • 62% of the project has been completed. Nevertheless its not granted that we will be able to finish on the proposed date. • In order to reduce the workload on the injection area during LS2, our proposal is to put in place the 16L1 magnets during the winter break: 2015/2016. L. Feliciano
Planning L. Feliciano
Milestones L. Feliciano
Kick Requirements Imagnet Slope 3 Slope 1 35 mm I1 I2 Slope 4 Slope 2 1 ms t2 t1 t 15 us -9.2 mm (1/5 BSW bump) DIS pulse up to 150 us L. Feliciano
Hardware - layout • As for the new hardware, the two major modifications that will come out are: • the 1L1 magnet stack will be removed from his present location to give room to the new injection system. • a new 16L1 magnet stack will be installed in between the bending magnet’s BHZ152 and BHZ161. • Other minor changes includes the move of the present 16L4 to replace the 2L1, which will be reconverted into spare. • As a result, the outer magnets 16L1 and 2L1 will be mechanically and electrically identical. Likewise for the inner ones 16L4 and 1L4. • All 8 new magnets as well as future spares will be equipped with new vacuum ceramic chambers. L. Feliciano
Hardware • Half Magnets • All 16 half magnets assembled. • Both structure assemblies are finished. L. Feliciano
Hardware - issues • Half Magnets • For the first two half's that were impregnated, the outcome was not acceptable: • both connector were broken • the other half shown deposit of silicone left over all around the magnet. • It was decided to create a cradle for the handling of the magnets and connectors protection. It is also done by us the isolation of the magnet for the impregnation. L. Feliciano
Hardware - issues • Ceramic vacuum chambers • Titanium deposit was not homogeneous. • No vacuum leaks were found. • Resistivity measurements shown that the values are out of spec. • Titanium deposit had to be removed at CERN due to incapability of the supplier to perform it, and then redone. L. Feliciano
Budget Metrics per year in kCHF L. Feliciano
Conclusions • Two new sets of four magnets with RF screens will be built. • The outer/inner magnets will be mechanically and electrically identical. • The same approach will be followed for the inner ones. • Although the project is late regarding to planned(end 2014), we still expect to be able to have the hardware ready before the 15/16 winter stop. L. Feliciano