160 likes | 325 Views
LIU-PSB Activities during LS1. The LIU-PSB Working Group https ://espace.cern.ch/liu-project/liu-psb/default.aspx. K. Hanke , LIU Day 2013, 12/04/2013. Cable Clean-Up and Identification. p roblem: full cable trays, impossible to pull cables for new equipment
E N D
LIU-PSB Activities during LS1 The LIU-PSB Working Group https://espace.cern.ch/liu-project/liu-psb/default.aspx K. Hanke , LIU Day 2013, 12/04/2013
Cable Clean-Up and Identification • problem: • full cable trays, impossible to pull cables for new equipment • manpower bottleneck during LS1 compromise: partial removal of unused cables where possible cable identification campaign (flagging cables that can be removed during an intermediate shutdown)
Cable Identification • documentation: • - layout of the BCER, BOR, BAT exists: (Drawings PS_EY___7001, 7002 and 7012) • - integration of the cable trays exists on Euclid • cable data base: • cables modified or installed after 1989 are inserted in the cable data base (6000 cables) • cables installed before 1989 are documented in hand-written lists (11000 cables) • during LS1, a campaign to identify the obsolete cables in the PSB will be coordinated by D. Hay and F. Chapuis • identify the obsolete racks; list of racks will be prepared, every equipment group responsible to mark unused racks. • identify the cables to remove; equipment owners have the responsibility during LS1 to mark the unused cables and the cables that will be obsolete after Linac4 connection.
Cable Campaign ProgressD. Hay, F. Chapuis So far cabling in the buildings BCER, BOR… This week or early next week tunnel work starts
Exchange of Main DumpA. Perillo Marcone, A. Sarrio Martinez • The existing Booster dump was installed during construction of the Booster (1968-1972); it is inappropriate for Linac4 intensities and 2 GeV • Having a new dump in place is a prerequisite for Linac4 connection • procedure to dismantle existing dump (ALARA) • installation of new dump including CV equipment towards the end of 2013 new dump: stress new dump: temperature
Exchange of Main DumpA. Perillo Marcone, A. Sarrio Martinez Current Shielding Current PSB Dump X New support Steel Shielding Concrete Shielding Air out Dump core (Cu) Air in
Beam InstrumentationJ. Tan et al • Position • - injection (LT, LTB and BI): • new system based on Linac4 standards; new monitors • (shorted strip lines), new cables (old ones removed), new • acquisition chain • - Booster orbit: • new cables for the new PSB orbit and trajectory system will not be pulled but this system will be installed and commissioned via existing OASIS channels with slightly reduced performance (s/n) for a selectable ring; old system remains as is • - extraction and transfer: • replacement of 10 remaining BPMs in BT, BTP, BTM and BTY (inductive PUs) • some upgrade of the already installed inductive PUs • Intensity • - injection (BI.BCT10 and 20 (x4)): • reduction of windings around the cores, for operation with very short Linac4 pulses • - PSB DCCTs: • consolidation (new electronics tested in LEIR) • - extraction and BTY lines: • change of BCTs including cables
Beam InstrumentationJ. Tan et al • Profile • - SEM: • SEM grids in the extraction and transfer lines to be equipped with new electronics and sw • - BWS: • general maintenance, calibration, some improvements (PMs, filters) • - BT.MTV10: • new tank (was before in BT.SMV10) • Beam Loss • first phase: installation of 32 LHC-type detectors • parallel installation to the operational system, two • detectors in each of the 16 PSB sections (L2) • Misc. • tune control improvement • some work related to dump exchange
Cable removal in the BCER Installation of rack supports PowerS. Pittet • exchange of Multipole Power converters is the outstanding activity • possibly install 4 new converters for BI1.SMV, BI2.SMV, BI4.SMV (+ 1 spare) Multipole converter signal & 400 V Cables • Phase 1 : Decabling campaign of the surface PSB Multipole converters completed • Phase 2 : Decabling campaign of the machine PSB Multipole converters started • Ancient multipole racks and power converters have been removed • New multipole rack supports are currently under construction
MagnetsA. Newborough • Upgrades to the main bending and quadrupole magnets are planned from September, upgrades will be made mainly to hydraulic circuits including reinforcing the quadrupole hydraulic connections and modifying the magnet interlocks. Quadrupole connections before and after the upgrade
RF • LL RF M.E. Angoletta • new Digital Beam Control installed in parallel with the existing beam control on all rings (plus a spare system) during LS1, which will be commissioned during the start-up after LS • RF Interlock system HW produced & tested in LS1, and will be installed ready for commissioning in September 2014 • TFB (A. Blas) • new Transverse Feedback system installed in parallel with existing TFB for all rings during LS1, commissioning and testing of the new system will take place until December 2014 • HL RF M. Paoluzzi • During LS1, 5 additional FINEMET cells are to be installed in R4 to bring the total to 10, all of which to be equipped with new power amplifiers. These will be commissioned and tested until December 2014
Beam TransferJ. Borburgh • Upgrade planned on BE.SMH: modification of under vacuum electrical connections and cooling to allow 2 GeV operation. • Exchange planned for November 2013 Whatever can be done during LS1, is one task less during LS2, when many other septa need to be replaced!
ControlsS. Jensen • ACCOR activity • after LS1 37 out of 42 FEs will be renovated • This corresponds to 88% of the FECs which will have to be commissioned after LS1
Front view of BIS rack Beam InterlocksC. Martin, B. Puccio (TE/MPE) • new ‘PSB Ejection’ Master BIC will be operational after LS1 • managing the four possible beam destinations: • BDUMP, PS, ISOGPS or ISOHRS • four input signals are reserved for these destinations (information available in the PSB telegram) • interlock conditions analyzed via a truth table that relates the acquisition values of main bending magnets with certain destinations v v extraction kickers are disabled when the ‘PSB Ejection’ Beam_Permit is FALSE First step in the re-design of the Linac4-PSB interlocks v
Magnet InterlocksP. Dahlen, R. Mompo (TE/MPE) • Warm magnet Interlock Controller (WIC) solution will be operational after LS1 • Standardized interlock system based on PLC (Siemens Safety Series): • already operational in LHC, SPS-LHC transfer-lines, LEIR & Linac3, and soon to be installed in Linac4. • PLC Programming & PVSS supervision in collaboration with EN/ICE-PLC. 4 controllers to protect & control 173 magnets and 177 Power-Converters. + 43 deported crates to collect the magnets inputs (Thermo-switches, water-flow switches,…) + 10 crates to provide Permit to Power-converters and collect their status and give Permit to Beam Interlock System
Not to be forgotten… • complete re-alignment of the machine and some of the transfer lines • renovation of the beam stopper control (EIS) • new access system • there is a lot of additional activity ongoing which is pure maintenance, consolidation, or not under the umbrella of LIU (e.g. new access system) • there is a lot of integration, preparation and design work ongoing e.g. for Linac4 connection (not LS1…) • Many thanks for your attention and for supporting us!