An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TDC2-TCC2 consolidationstatus report 08.04.2014 S. EVRARD, EN-MEF

  2. 2014 Schedule ALARA L3 Committee

  3. Removal of hot items • Removal of hot items from the worksites: • TCSC removed first and brought to B.955 • 3 splitter2 magnets and 2 MDLV removed and stored in TDC2 • Various beam monitors, BLM and vacuum beam pipes

  4. Removal of hot items: storage area = forbidden area 3 splitter2 magnets 2 MDLV magnets

  5. Splitter area • First removal of splitter magnets in TDC2 since mid seventies • Some trouble due to floor imperfecti-ons

  6. MDLV & beam pipes • About 100 m beam pipes removed • Make free the splitter storage area • Make free the area where heavy duty works will take place

  7. Beam instrumentation ALARA L3 Committee

  8. Chilled water pipes & coils removal • About200 m DN 200 insulated pipe have been dismantled • Asbestos successfullyhandled as expected. • CoolingcoilsalsoremovedfromAHU’s • Cabinet (40 yearsold) quite in good shape • Radioactive waste management ALARA L3 Committee

  9. Secondary beam line vacuum maintenance • Exchange of the oil in all the vacuum pumps. • Installation of 4 new vacuum pumps • PVSS control check • Leakdetection • Pressure gauge check (recalibrationneeded no leakinthe M2 line) • New platform for relocation of the 2 M2 line vacuum pumps(betteraccess) ALARA L3 Committee

  10. Civil Engineering: repair of the TDC2 roof joints • 2 joints have been fitted with a metallic gutter driving water and bitumen to 3 retention boxes. TDC2WG#31

  11. Civil Engineering: drain network maintenance • Vallier checked all the manholes and inspection chambers • High pressure cleaning • Cleaning water collected and RP checked before disposal • Sludge treated as radioactive waste ALARA L3 Committee

  12. Civil Engineering: variousrepairs • New, extension of, repair to water collecting gutters • Exchange of all remaining PVC pipes by PE pipes • New drain connection • Removal of all wood items by steel plates (trenches for cabling purpose) ALARA L3 Committee

  13. Safety system upgrade • Relocation and exchange of the Fire extinguishers • New evacuation path layout and signals put accordingly • Guided tour with the Fire Brigade ALARA L3 Committee

  14. Heavy handling equipment • PR544 maintenance and test • Power supply rail inspected: some corrective actions needed (due to verybrittle plastic insulation) ALARA L3 Committee

  15. Magnet upgrade • One manifold dismounted (ref 12) in order to estimate time needed for exchange • Cooling flexible replacement in progress in TDC2 • 12 DC cable joints to bereplaced (seeYvan’s talk) ALARA L3 Committee

  16. Beam line survey • 12 concrete blocks 800*800*800 to be removed • Openings towards TT81 and TT82 • Measurement of all the beam line equipment • Including XTAX tables once roof shielding is removed • Up to targets ALARA L3 Committee

  17. Cabling EN-EL schedule • 31/3 WDP assessment for Alara level • 31/3-21/4 preparation Dry Run presentation • 22/4 Dry Run discussion within CF Section • 28/4 ENTM Dry Run • 12/5 Alara Committee (if the study confirms to be a level III) ALARA L3 Committee

  18. Lighting study in TDC2 ALARA L3 Committee

  19. Lighting study in TCC2 CoreLineHighbay Philips ALARA L3 Committee

  20. Target refurbishment • Proximitycabling has been removed • New monitors and targetboxes underassembly in EHN1 cleanroom. • Shielded container in production ALARA L3 Committee

  21. EDMS 1355301 Damien GRENIER North Area Targets Consolidation LS1 12/02/2014 40% progress EN/STI/TCD Technical Schedule Budget Description Remplacement de tous les équipements des Cibles T2,4,6,10 ainsi que le cablage et patch panel Schedule Milestones Progress Nextsteps Deliverable -Fabrication de 12 TBIU/D, 8 BAC, 2 Collimateurs T10, 8 motorisationsblindage mobile, remplacement de 6 debimetres Team members EN/STI: FSU, J. Lendaro, M. Donze, D. Grenier BE/BI: C. Vuitton, etc… TE/VSC: J. Kortesmaa, etc… Points à suivre de près: -Soudure FE Coll T10 -Plaques Be hors tolerance -Guide a billes QUAD -Fournitures manquantes -Nettoyage, traitements surface Pré-assemblageau EHN1 Template: EDMS 1341350 - v0.2

  22. Worksite logistics • Wi-Fi and Ethernet connections available in TA801 and soon at the shaft surface (waste management) • Floor contamination monitoring: nothing seen up to now. • New lead panels available for TDC2. ALARA L3 Committee

  23. RP survey • EDMS 1319247 TDC2WG#31

  24. Collective dose management ALARA L3 Committee