TDC2-TCC2 consolidation status report to EATM. 04.03.2014 In sharepoint: https://espace.cern.ch/sba-workspace/tcc2wg/LS1%20worksite%20meeting/. S. EVRARD, EN-MEF. Outline. 2014 schedule Worksite progress Dedicated working groups. 2014 Schedule. Removal of hot items.
E N D
TDC2-TCC2 consolidationstatus report to EATM 04.03.2014 In sharepoint: https://espace.cern.ch/sba-workspace/tcc2wg/LS1%20worksite%20meeting/ S. EVRARD, EN-MEF
Outline • 2014 schedule • Worksite progress • Dedicated working groups
2014 Schedule ALARA L3 Committee
Removal of hot items • Removal of hot items from the worksites: • TCSC removed first and brought to B.955 • 3 splitter2 magnets and 2 MDLV removed and stored in TDC2 • Many beam monitors, BLM and vacuum beam pipes
Removal of hot items 3 splitter2 magnets 2 MDLV magnets
Beam instrumentation ALARA L3 Committee
Chilled pipes exchange ALARA L3 Committee
Secondary beam line vacuum maintenance • Nous avons remplacé l’huile des pompes à palettes et remplacer 4 pompes à vide dans le cadre de la rénovation. • Apres contrôle par PVSS il reste à contrôler le vide sur place au niveau de chaque pompe à vide • Placer une plateforme pour déplacer les deux pompes du M2, (fabrication à l’atelier 887) • détection de fuite ALARA L3 Committee
Dedicated working groups • LV systems and Cabling • XTAX repair ALARA L3 Committee
Cabling detailed study ALARA L3 Committee
Cabling EN-EL schedule • 31/3 WDP assessment for Alara level • 31/3-21/4 preparation Dry Run presentation • 22/4 Dry Run discussion within CF Section • 28/4 ENTM Dry Run • 12/5 Alara Committee (if the study confirms to be a level III) ALARA L3 Committee
Life expired equipment LV systems
XTAX repair Solutions Poussoir a ressort (maintient de la coupelle pendant le levage) Remplacement des pattes de guidage par une surface d’appui complète Coupelle de positionnement Nouveau soufflet (Plus grande course) Vérin Nouvelle tête de vérin