1 / 38

Kania SOM / Brennan Hall

This presentation outlines the construction process and structural design of KaniaSOM/Brennan Hall, a five-story office/classroom building at the University of Scranton. It covers information technology, wireless LAN, loads, lateral system, gravity system, scheduling/cost, and more.

hhendershot
Download Presentation

Kania SOM / Brennan Hall

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Kania SOM / Brennan Hall University of Scranton - Scranton, Pennsylvania Douglas Wisniewski Structural Option

  2. KaniaSOM / Brennan Hall Presentation Outline • Project Background • Introduction • Project Team • Construction • Structure • Information Technology • Wireless LAN Breadth Study • Wireless LAN • Access Points • IP Phones • Interactive Whiteboards • Video Conferencing • Structural Depth Study • Loads • Lateral System • Gravity System Conclusions Acknowledgements Questions • Scheduling/Cost Breadth Study • Material Costs • Construction Schedule • Final Cost Figures

  3. KaniaSOM / Brennan Hall Project Background • Introduction • Five-story office/classroom building • 68,500 square feet • $12.3 million project • 1st and 2nd floors primarily classrooms • 3rd and 4th floors primarily faculty offices • 5th floor executive board room and catering facilities

  4. KaniaSOM / Brennan Hall Project Background • Project Team • Owner – University of Scranton • Architects – Burkavage Design Associates • Structural Engineer – QproQ Engineering, Inc. • Geotechnical Consultant – Geo-Science Engineering • General Contractor – Sordoni Construction Services

  5. KaniaSOM / Brennan Hall Project Background • Construction • Started March 1999 • Completed August 2000 • CM at risk delivery method • Adjacent dorms constructed at same time • Subcontractor lump sum bids

  6. KaniaSOM / Brennan Hall Project Background • Structure • Structural steel framing • Fully rigid moments frames • Concrete-filled composite metal deck • Column spread and continuous wall footings

  7. KaniaSOM / Brennan Hall Project Background • Information Technology • Showcase instructional technologies and conference center flexibility • Touch screen control of lighting, computing, and audio/video components • Overhead projector, motorized screens, image visualizers, DVD & CD players • High-end video displays, theater like sound and video conferencing in executive conference center • Auditorium featuring theater like audio and video environments

  8. KaniaSOM / Brennan Hall Presentation Outline • Project Background • Introduction • Project Team • Construction • Structure • Information Technology • Wireless LAN Breadth Study • Wireless LAN • Access Points • IP Phones • Interactive Whiteboards • Video Conferencing • Structural Depth Study • Loads • Lateral System • Gravity System Conclusions Acknowledgements Questions • Scheduling/Cost Breadth Study • Material Costs • Construction Schedule • Final Cost Figures

  9. KaniaSOM / Brennan Hall Structural Depth Study • Loads • From AISC Manual of Steel Construction • Dead loads • Roof dead (no ballast) 16.7 psf • Roof dead (with ballast) 26.7 psf • Floor dead 100 psf From ASCE 7-02 • Live loads • Corridors 80 psf • Classrooms 40 psf • Offices 50 psf • Snow load 30 psf

  10. KaniaSOM / Brennan Hall Structural Depth Study • Loads • As Calculated by RAM Frame • Wind loads N-S E-W • Roof level 12.2 kips 14.4 kips • Fifth Floor 21.5 kips 22.9 kips • Fourth Floor 20.5 kips 21.7 kips • Third Floor 21.7 kips 19.9 kips • Second Floor 22.5 kips 18.3 kips • Total 98.4 kips 97.2 kips • Seismic loads • Total Building Weight 5690 kips • N-S Base Shear 246.7 kips • E-W Base Shear 284.5 kips

  11. KaniaSOM / Brennan Hall Structural Depth Study • Lateral System • Goals for proposed system • Eliminate high cost of steel moment connections • Reduce steel erection time by eliminating steel moment connections • Initially four shear walls • Two located on each of two opposing corners • Very rigid, very small drift • High lateral loads caused overturning moment problems

  12. KaniaSOM / Brennan Hall Structural Depth Study • Lateral System • Combat overturning moments by • Adding two additional shear walls • Decrease lateral load to each wall • Increasing wall thickness • Increase mass for resisting moments • Increasing wall footing sizes • Increase mass for resisting moments

  13. KaniaSOM / Brennan Hall Structural Depth Study • Lateral System • Designed as deep cantilever beams • Reinf. generally controlled by minimum steel areas • Exterior walls also designed for wind pressure

  14. KaniaSOM / Brennan Hall Structural Depth Study • Gravity System • Goals for proposed system • Reduce weight of floor system • Improve efficiency of floor system • Replace wide flange infill beams with open web steel joists • Concerns • Fire Protection • Floor Vibrations

  15. KaniaSOM / Brennan Hall Structural Depth Study Gravity System Typical joist layout Joists oriented to span long dimension of bay for economy

  16. KaniaSOM / Brennan Hall Structural Depth Study • Gravity System Fire Protection • Difficult for spray-applied fireproofing to adhere to joist webs • Design No. G708 from U.L. Fire Resistance Directory • 2 hour fire rating • W8X28 min. beam size • Normal weight concrete, f’c = 3500 psi • Form deck with 2 ½” pitch, ½” corrugations • min. 16K6 joists spaced at 3’-6” max. • Spray-applied fire resistive material • Metal lath (optional)

  17. KaniaSOM / Brennan Hall Structural Depth Study • Gravity System Fire Protection • Design No. G708 from U.L. Fire Resistance Directory

  18. KaniaSOM / Brennan Hall Structural Depth Study • Gravity System Floor Vibrations • Calculations based on AISC’s Design Guide 11 • Applied loads • Live load 11 psf • Misc. 4 psf • Floor stiffness evaluation • Combined mode frequency 4.8 Hz • Not needed since less than 9 Hz • Walking evaluation • Peak acceleration 0.43%g • Less than office limit of 0.5%g

  19. KaniaSOM / Brennan Hall Presentation Outline • Project Background • Introduction • Project Team • Construction • Structure • Information Technology • Wireless LAN Breadth Study • Wireless LAN • Access Points • IP Phones • Interactive Whiteboards • Video Conferencing • Structural Depth Study • Loads • Lateral System • Gravity System Conclusions Acknowledgements Questions • Scheduling/Cost Breadth Study • Material Costs • Construction Schedule • Final Cost Figures

  20. KaniaSOM / Brennan Hall Scheduling/Cost Breadth Study • Cost analysis to evaluate lateral system • Material Costs • Materials added • Reinforced concrete shear walls • Wall footings • Materials removed • Spread footings • Moment connections • Steel beams • Steel columns

  21. KaniaSOM / Brennan Hall Scheduling/Cost Breadth Study Material Costs Shear Walls New wall footings and spread footings removed

  22. KaniaSOM / Brennan Hall Scheduling/Cost Breadth Study Material Costs Shear connections replacing moment connections Steel beams and columns removed Total material cost savings of nearly $25,000

  23. KaniaSOM / Brennan Hall Scheduling/Cost Breadth Study • Construction Schedule • Sequencing shear wall construction • Formwork erection • Concrete placing and finishing • Strip and rebuild forms • Time saved in steel erection • Fewer steel members • No moment connections • Sequencing with foundation construction • Time for concrete walls to reach 80% strength • Steel attached to concrete walls

  24. KaniaSOM / Brennan Hall Scheduling/Cost Breadth Study • Detailed shear wall construction sequence • Two formwork crews • Sequence forming and placing

  25. KaniaSOM / Brennan Hall Scheduling/Cost Breadth Study Construction Schedule Shear wall construction costs Steel erection costs Total construction costs nearly $128,000

  26. KaniaSOM / Brennan Hall Scheduling/Cost Breadth Study • Final Cost Figures • Combination of material and construction costs • Reinforced concrete shear walls result in nearly a $103,500 increase in total project cost • However, amounts to less than a 0.9% increase

  27. KaniaSOM / Brennan Hall Presentation Outline • Project Background • Introduction • Project Team • Construction • Structure • Information Technology • Wireless LAN Breadth Study • Wireless LAN • Access Points • IP Phones • Interactive Whiteboards • Video Conferencing • Structural Depth Study • Loads • Lateral System • Gravity System Conclusions Acknowledgements Questions • Scheduling/Cost Breadth Study • Material Costs • Construction Schedule • Final Cost Figures

  28. KaniaSOM / Brennan Hall Wireless LAN Breadth Study • Wireless LAN • Goals for proposed system • Less wire and cable throughout building • More flexible system • Reduce overhead costs caused by moves, extensions to networks, adding connections • Can serve as hot spot for students with laptops • Can connect other buildings to same network • Installing network in older buildings is easy • 802.11a • Selected over 802.11b & g standards • 64 users per access point • Lower possibility of interference • Good for; dormitories, computer labs, conference rooms, VoIP

  29. KaniaSOM / Brennan Hall Wireless LAN Breadth Study Access Points • Analyzed • layout • # of users Determined # of AP’s AP AP AP AP AP AP SC SC AP AP AP AP AP AP AP AP

  30. KaniaSOM / Brennan Hall Wireless LAN Breadth Study Integrated IP Phone System • PC Based Phones • Software allowing computers to be used as IP phones • Each individual’s extension follows them to any computer • Teleconferencing capabilities • Desktop IP Phones • Connected via Ethernet to wired backbone • Located in secretary and waiting areas • Wireless IP Phones • Used by physical plant employees

  31. KaniaSOM / Brennan Hall Wireless LAN Breadth Study Interactive Whiteboards • Replaces chalkboard, overhead projector and screen • Can function simply as a whiteboard • Can display computer images • Can save handwritten notes to print or post on course websites Video Conferencing • Located in executive conference center • Built in conferencing with multiple video and audio sites • Dual LCD monitors • Add a PC to the meeting • See live PC presentations and presenter simultaneously

  32. KaniaSOM / Brennan Hall Presentation Outline • Project Background • Introduction • Project Team • Construction • Structure • Information Technology • Wireless LAN Breadth Study • Wireless LAN • Access Points • IP Phones • Interactive Whiteboards • Video Conferencing • Structural Depth Study • Loads • Lateral System • Gravity System Conclusions Acknowledgements Questions • Scheduling/Cost Breadth Study • Material Costs • Construction Schedule • Final Cost Figures

  33. KaniaSOM / Brennan Hall Conclusions • Conclusions • Structural Depth Study – Lateral System • Lateral system consisting of six reinforced concrete shear walls • Very rigid, little drift • Larger wall footings needed for overturning • Was a successful educational project • Learned how to design shear walls • Scheduling/Cost Breadth Study • Additional crews and equipment needed for five weeks to construct shear walls • Steel erection shortened four days • Shear walls increased total project cost by $103,500 • Less than a 0.9% increase

  34. KaniaSOM / Brennan Hall Conclusions • Conclusions • Structural Depth Study – Gravity System • Economic joist layout • More efficient floor framing • Two hour fire rated ceiling assembly • Adequate for floor excitation • Wireless LAN Breadth Study • More flexible network solution • Access points located throughout building • IP telephony available from any networked computer • Instructional spaced equipped with interactive whiteboards • Sophisticated video conferencing units in executive conference center

  35. KaniaSOM / Brennan Hall Presentation Outline • Project Background • Introduction • Project Team • Construction • Structure • Information Technology • Wireless LAN Breadth Study • Wireless LAN • Access Points • IP Phones • Interactive Whiteboards • Video Conferencing • Structural Depth Study • Loads • Lateral System • Gravity System Conclusions Acknowledgements Questions • Scheduling/Cost Breadth Study • Material Costs • Construction Schedule • Final Cost Figures

  36. KaniaSOM / Brennan Hall Acknowledgements • I would like to thank • James Devers, AIA, U of S Physical Plant • Don Flynn, Burkavage Design Associates • Linda Hanagan, PhD, PE, Penn State University • James Kerns, PE, QproQ Engineering • Francis Kranick, U of S Physical Plant • M. Kevin Parfitt, Penn State University • Andrew Shedlock, Sordoni Construction • Ronald Skutnick, U of S Network Resources • David Wilson, AIA, U of S Physical Plant • David Wisniewski, Raytheon For all of the time and information they have contributed to this project.

  37. KaniaSOM / Brennan Hall Presentation Outline • Project Background • Introduction • Project Team • Construction • Structure • Information Technology • Wireless LAN Breadth Study • Wireless LAN • Access Points • IP Phones • Interactive Whiteboards • Video Conferencing • Structural Depth Study • Loads • Lateral System • Gravity System Conclusions Acknowledgements Questions • Scheduling/Cost Breadth Study • Material Costs • Construction Schedule • Final Cost Figures

  38. KaniaSOM / Brennan Hall Questions ?

More Related