230 likes | 386 Views
Using Most Probable Cost As A Part Of The Source Selection Evaluation Process. Bill Haseltine President, Society of Cost Estimating & Analysis (SCEA). November 6, 2009. Luke 14:28-30.
E N D
Using Most Probable Cost As A Part Of The Source Selection Evaluation Process Bill HaseltinePresident,Society of Cost Estimating & Analysis (SCEA) November 6, 2009
Luke 14:28-30 For which one of you, when he wants to build a tower, does not first sit down and calculate the cost to see if he has enough to complete it? Otherwise, when he has laid a foundation, and is not able to finish, all who observe it ridicule him, saying “this man began to build and was not able to finish.”
OUTLINE • What is Cost Estimating & Analysis • Life Cycle Composition • Estimate Definitions • Cost Estimating Basics • Challenges • Cost Reasonableness & Realism • Sample Section M • Integration of Cost Risk & Oversight
What is Cost Analysis & Estimating? Cost Analysis & Estimating is an Analytical Process employed to predict the resource requirements for Weapon System Programs considering both: Qualitative and Quantitative Factors Guidelines = PPBS and DOD 5000.4 Frameworks
Life Cycle Cost Composition Life Cycle Cost Estimate Program Acquisition Cost RDT&E, PROC, MILCON, O&M, & MILPERS Procurement Cost RDT&E, PROC & MILCON, PROC only Weapon System Cost PROC only • Initial Spares Flyaway Cost • Facilities • Operations Support (includes Post Production Support) • Disposal RDT&E & PROC • Tech Data • Publications • Contractor Services • Support Equipment • Training Equipment • Factory Training • Management • Hardware • Software • NRE “Startup” • ECOs • IACO
Estimate Definitions • Life Cycle Cost Estimate (LCCE) includes ALL Phases and ALL years: • Development (usually RDT&E) • Procurement (usually Investment) • Operations & Support and Disposal (O&M) • Types of LCCEs • PMO Estimate • Independent Cost Estimate (ICE) (i.e side by side) • Independent Cost Analysis (ICA)
Estimate Definitions (cont.) • FYDP Estimate • Development • Production • O&S • All or some of the above • Planning Estimate (or “What-If” Exercise) • Drill • Portion of one of the phases • Cost Benefit Analyses • Acquisition should cost • Estimate Assessments • Qualitative • Sufficiency Review
Estimate Definitions (cont.) • Independent Government Cost Estimate (IGCE) • Completed prior to receipt of proposals • Detailed Technical Baseline including: • Assumptions, • Schedule • Detailed Work Breakdown Structure (WBS) • Detailed WBS Dictionary • Cost mapped to Contract Line Items (CLINs) • Addresses Government Furnished Equipment (GFE) • Most Probable Cost Estimate (MPC) • Ties back to IGCE • Part of Source Selection Evaluation effort • Broken out by Contract Line Items (CLINs) • Government Furnished Equipment (GFE) • Adjustments for cost realism, risk & missing items
Cost Estimating Methodologies • Parametrics: • Statistically based equations relating technical & performance parameters to $$$. Price model Example • Analogy to a similar system(s): • Use data from comparable systems and adjust it for unique aspects or differences. • Engineering Build-Up: • Estimates based on scope of work and technical understanding of each task to be accomplished WBS by WBS.
Data Requirements • Parametrics: • Built on multiple program data sets • Analogy to a similar system(s): • Crucial to have the actual cost data from comparable systems. • Engineering Build-Up: • Must have reliable cost data for each WBS that builds to the estimate. Critical to have Actual contract data for each estimating approach!!!!!
Steps Involved In Cost Realism Analysis Step1: Determine if cost realism analysis is required. Step 2: Gather information Step 3: Conduct analysis Step 4: Perform risk assessment Step 5: Advise offeror of findings during discussions Step 6: Allow revised proposal (repeat analysis) Step 7: Adjust proposed cost to MPC Step 8: Use results as stated in the RFP
Technical & Programmatic Baseline Technical: • Work Breakdown Structure (WBS) ….DETAILED • Hardware & Software Elements • Physical and Performance Characteristics • Description of State-of-the-art Technology • New design vs Modified vs off-the-shelf • Commonality to Existing Systems • Programmatic: • Acquisition Strategy • Schedule • Quantities • Contractors & Subcontractors • Make vs Buy • GFE vs CFE • Milestones • Appropriation Phasing Cost Analysis and Estimating Process PMO LCCE ICE LCCE FYDP Estimate Planning Estimate Assessment
Point Estimates VersusProbability Distributions • Risks are assessed at the lowest possible WBS level, and • Aggregated by program phase to determine the probability distribution • Uncertainty is GUARANTEED, and • Point Estimates will ALWAYS be WRONG !!!
Sample Risk Assessment Matrix Technical Schedule Cost Overall PMP – Design PMP – Prototypes PMP – S/W Development SEPM Data Tooling & Factory Test Equip. ST&E Government Operational T&E Gov’t Program Office Expense KEY: High Moderate Low