1 / 25

Eastern Nevada Transmission Intertie (EN-ti)

Eastern Nevada Transmission Intertie (EN-ti). January 24, 2008 Las Vegas, NV. Eastern Nevada Transmission Intertie (EN-ti) Path Rating Study, Phase II Colorado River Transmission Study Group Meeting, . Agenda. EN-ti and EEC: Description EN-ti and EEC: Current project status

hillary
Download Presentation

Eastern Nevada Transmission Intertie (EN-ti)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Eastern Nevada Transmission Intertie (EN-ti)

  2. January 24, 2008 Las Vegas, NV Eastern Nevada Transmission Intertie (EN-ti) Path Rating Study, Phase IIColorado River Transmission Study GroupMeeting,

  3. Agenda • EN-ti and EEC: Description • EN-ti and EEC: Current project status • EN-ti and EEC: Design study results • WECC Rating Review Process: Current status • Phase II Study: • Study Scope & Plan • Non-Simultaneous & Simultaneous EN-ti to Centennial case preparation • Comments received & case corrections • Contingency analysis • Next Steps

  4. Ely Energy Center and Eastern Nevada Intertie Project: Nevada Map

  5. Ely Energy Center & EN-ti Projects • EEC 500 kV Switching Station • EEC – Robinson Summit 500 kV No. 1 & 2 Transmission Lines • Robinson Summit 500/345 kV Switching Station • Fold of Falcon – Gonder 345 kV Line Into Robinson Summit Substation • Series compensation on Falcon – Gonder 345 kV Line • Harry Allen – Robinson Summit 500 kV No. 1 Transmission Line: “Eastern Nevada Transmission Intertie” (EN-ti): 236 mi, 70 % series compensated, reactors, single-pole switching • Harry Allen 500 kV Improvements for EEC/EN-ti

  6. Simplified Robinson Summit Substation One-line Diagram

  7. White Pine Energy Center / Great Basin Transmission Interconnection

  8. Purpose and Justification of the EN-ti & EEC Projects • Interconnect SPPC and NPC Systems • 1,550 MW of new resources to Nevada Power loads • 300 MW of new resources to Sierra Pacific loads • Deliver renewable energy & future IGCC to Southern Nevada • Possible interconnection to the North (toward Midpoint 500-kV) • Interconnect White Pine Energy Center • Point-to-point transmission service for Great Basin Transmission additions

  9. Ely Energy Center and Eastern Nevada Intertie Project: One-Line Diagram

  10. EN-ti & EEC Project Status En-Ti Rating Process Description • Project initiated in 2006 • BLM Line & Plant permitting status: • In process (cultural surveys underway) • Is expected to take 7 months to 1 year longer, which would likely delay the project, with the COD of EEC unit # 1 to be moved at least from 2011 to 2012 • EIS Plant permitting: in process; SPR is about to obtain the air quality permit

  11. EN-ti & EEC Project Status (Continued) En-Ti Rating Process Description • Specifications for series compensation and shunt reactors are in process • Long-lead equipment production slots are reserved • Design Study: underway EMTP, PSS, SSR studies; a number of alternatives is still under consideration • Major Equipment: Specifications for autotransformers, PSTs finalized • Generation: SPR prepared RFPs, initiated bids for major equipment (boilers, turbine generators)

  12. EN-ti & EEC Design Studies: Major Results En-Ti Rating Process Description • EN-ti Series and shunt compensation: • Line over-voltages due to step-voltages at the series capacitors terminals (see Figure 1) • Recommended: increase EN-ti line max insulation level from 550 kV to 600 kV • Single-pole reclosing (secondary arc extinguishing) and line energization conditions • Recommended: Shunt reactors: 2×100 Mvar + 1,200 Ω neutral reactors at each end of EN-ti line • Recommended: Shunt reactors: 48 Mvar at Falcon and Robinson 345 kV

  13. EN-ti Voltage Profile Under Heavy Loads Figure 1:

  14. EN-ti & EEC Design Studies: Major Results (Continued) • Defined voltage domains of EN-ti and 345 kV system for normal operation (see Figure 2), which revealed additional operational constraints • Recommended: set Robinson – Falcon transfer limit to 600 kV and install a 48 Mvar bus reactor at Falcon 345 kV

  15. EN-ti & 345 kV RS-Falcon Voltage Profiles Figure 2: Normal Operations Voltage Domains

  16. EN-ti & EEC Design Studies: Major Results (Continued) • Delayed current zeros: EEC BKR clearing time increased to ~5 cycles • Recommended: specify 500 kV BKRs at EEC to have a capability to interrupt fault current in a network configuration that has a very high X/R ratio, which produces two effects that are detrimental to breaker fault current interruption: • delayed current zeros, and • high dc offset.

  17. EN-ti & EEC Design Studies: Major Results (Continued) • Major Equipment at Robinson Summit : • Autotransformers: 2×525 MVA (E=840MVA) • PSTs: 2×600 ±48°; Transformers and PSTs impedances Z=4% (based on angular stability requirements) • EMTP, PSS: currently are ongoing • SSR studies: ongoing (frequency scans, etc.). Bypassing of SC @ Robinson or TCSC may be required

  18. EN-ti WECC Rating Review and Study: Status En-Ti Rating Process Description • SPR Initiated WECC Regional Planning Process, Regional Review Group Formed in Jan-2006 • Initiated Phase I in Oct-2006 • Comprehensive Progress Report Phase I submitted on Nov-9-2006 and approved by the PCC chair on Feb-26-2007 after 60-days review

  19. EN-ti WECC Rating Review and Study: Status (Continued) En-Ti Rating Process Description • Regional Project Report submitted on Jan-25-2007 and approved by the PCC chair on Feb-26-2007 after 30-days review • Phase II Status to EN-ti Project has been granted on March 02, 2007

  20. EN-ti Phase II Project Review Group

  21. Phase II Study Cases Phase II EN-ti Study • Non – Simultaneous cases • Pre-Project, 2014hs • N-S 2,000 MW, 2014hs; 2X750MW @ EEC + 2,000 MW from SPPC to NPC CA + EN-ti (studied at Phase I) • S-N 1,000 MW, 2014hs; 0 MW @ EEC + 1,000 MW from NPC to SPPC CA + EN-ti

  22. Phase II Study Cases (Cont) Phase II EN-ti Study • Simultaneous EN-ti North to South & Centennial case • Created by stressing Centennial to 3,000 MW (new definition used) in the N-S non-simultaneous case • 2014hs; EN-ti N-S 2,000 MW + Centennial 3,000 MW; 2X750MW @ EEC + 2,000 MW from SPPC to NPC CA + EN-ti

  23. Phase II Study Cases (Cont) • Revisions 0 – 2 have been sent to the PRG & WATS electronically in February – March 2007 and responses and comments received and included in the Study Plan. All three cases were discussed during WATS/PRG teleconference on April-17-2007 • Updated cases were sent out for PRG/WATS review on 10/23/07 and again, after USE/SDG&E/SCE comments and respective corrections on 12/03/07

  24. Next Steps Rating Study Status Study Scope Study Results Next Steps • Complete transient and post- transient studies for non-simultaneous and Centennial cases • EOR/WOR/Path 63 • TOT2B/2C • GBT 500 kV Line • Sensitivities

  25. Questions?Thank you For Listening and Participating!

More Related