1 / 11

Puget Sound Area Northern Intertie (“PSANI”) Transmission History

Puget Sound Area Northern Intertie (“PSANI”) Transmission History. ColumbiaGrid September 24, 2007 Snohomish County Public Utility District John D. Martinsen. PSANI History. Historical BPA Plans April 2003 Curtailments Meeting of the Minds Current Status. Historical BPA Plans.

vian
Download Presentation

Puget Sound Area Northern Intertie (“PSANI”) Transmission History

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Puget Sound AreaNorthern Intertie (“PSANI”) Transmission History ColumbiaGrid September 24, 2007 Snohomish County Public Utility District John D. Martinsen

  2. PSANI History • Historical BPA Plans • April 2003 Curtailments • Meeting of the Minds • Current Status

  3. Historical BPA Plans • Excerpts from the BPA 1991 – 2000 Transmission System Facilities Ten Year Development plan • King County System Reinforcements (second Monroe to Echo Lake 500kV) • Planned energization in 1997 • Puget Sound Area Reinforcement (double circuit Chief Joseph to Monroe upgraded to 500kV & tie to Snohomish ) • (Planned energization in 2000) • Little support for new transmission during this period due to regulatory uncertainty – NEPA 1992

  4. King County System Reinforcements • …New Monroe to Echo Lake 500kV line • Reinforcement is required to eliminate the heavy loading on the underlying 230kV system during an outage of the existing Monroe-Echo Lake

  5. King County System Reinforcements

  6. Puget Sound Area Reinforcement • Replace existing Chief Joseph – Monroe 345kV double circuit lines with a 500kV double circuit line to Monroe and Snohomish • ..capacity may not be sufficient beyond 2000 if load growth is higher than expected or the Canadian Entitlement return must be delivered to Blaine

  7. Puget Sound Area Reinforcement

  8. April 2003 - Curtailments • April 2003 the Canadian Entitlement return increased from 630MW to 1,149MW • Curtailments and curtailment notices became a regular occurrence for Puget Sound utilities and Powerex

  9. Meeting of the Minds • Soon after April 2003 BPA, Puget Sound utilities, and Powerex met • A short-term Redispatch was agreed to by the Puget Sound and Powerex parties • The Puget Sound Area Study Group (“PSASG”) was formed under the Northwest Power Pool (“NWPP”) Northwest Transmission Assessment Committee (“NTAC”) • Puget Sound Area Upgrade Study Report was completed by the PSASG -November 2004

  10. Current Status • The Canadian Entitlement may increase to 1500 MW • Puget Sound Area loads are growing • Both wire and non-wire alternatives have been reviewed • Most of the major Transmission reinforcements reviewed would take eight to ten years to complete • Incremental upgrades and operating procedures have resulted in reduced curtailment risk • No major (i.e. 500 kV) Puget Sound area transmission expansion is currently moving forward

  11. Canadian Entitlement Returns

More Related