1 / 34

Northwest Colorado Oil and Gas Forum

Northwest Colorado Oil and Gas Forum. BLM/USFS Update, Sept 4, 2008. Drilling Permits 2008. Drilling Permits in 2008. Drilling Permits in 2008. Glenwood Springs Energy Office. 260 APDs in FY 08 to date: Williams 144 Laramie 17 Antero 6 EnCana 55 Noble 30

hoai
Download Presentation

Northwest Colorado Oil and Gas Forum

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Northwest Colorado Oil and Gas Forum BLM/USFS Update, Sept 4, 2008

  2. Drilling Permits 2008

  3. Drilling Permits in 2008

  4. Drilling Permits in 2008

  5. Glenwood Springs Energy Office 260 APDs in FY 08 to date: • Williams 144 • Laramie 17 • Antero 6 • EnCana 55 • Noble 30 • Orion 4 • Plains 4

  6. Glenwood Springs Energy Office: Master Development Plans (GAPS) • Orchard II GAP (25 new well pads, 1 existing, 95 wells) Decision expected this month • Spruce Creek, 4 multi-well pads, Comment period closed in July

  7. Master Plans of DevelopmentPre-planning stage • Gibson Gulch, 15-20 multi-well pads • Kokopelli, 15-20 multi-well pads, scoping this fall

  8. Glenwood Springs: Roan Plateau Aug 14 lease sale generated $113.9 million Won’t issue leases until protests are resolved

  9. Glenwood Springs/Kremmling RMP revisions • Drafts out in Fall 2009

  10. Grand Junction: APDs • 33 APDs to dateFY 08 Delta 17 Black Hills 5 EnCana 1 Plains Exp 9 Walter S Fees Jr 1

  11. Multiple-well EAs • Black Hills Horseshoe Canyon – Decision Sept or Oct Winter Flats – Approved in July Homer Deep – Decision expected this month • Aspen Operating (Whitewater) Scoping in June, working on EA

  12. Multiple-well EAs • Oxy (Bowdish) Working on EA • Retamco (Roan Creek) Revised MDP • Delta (Vega II) Waiting on MDP • PXP Plateau Valley – Waiting on MDP Hightower – Decision from USFS expected this month (32 wells on GMUG)

  13. Grand Junction • Whirlwind Uranium Mine: EA and Decision expected this month • CAM/Red Cliff Coal Mine Draft EIS expected this month • October Uranium Mine Plan/Reclamation decision expected this month

  14. Collbran Pipeline • 22-mile, 30-inch pipeline • 5 miles west of Collbran to 6 miles NE of DeBeque (Orchard Unit compressor site) • Decision and EA expected later this month

  15. Additional pipelines XCEL (Garmesa 16" pipeline) – Scoping through Sept. 5, decision projected for late October Enterprise (Logan Wash 16" pipeline) – Scoping through Sept 12, decision expected later this year

  16. White River: 172 APDs • BOPCO 25 • ExxonMobil 72 • Williams Production 28 • Chevron 5 • Conoco Phillips 27 • Whiting 8 • C&J Field Services 1 • XTO Energy 1 • Genesis 1 • KJH 1 • Robert Bayless 1 • Samson Resources 1 • Eden Energy 1

  17. Drilling Permits in 2008

  18. White River: RMP Amendment • Addresses anticipated increase in oil and gas development • 90 day public review for Draft EIS in fall 2009

  19. Oil Shale • Programmatic EIS Draft on Oil Shale and Tar Sands Final EIS should be released today • Final decision by end of year • Final decision on commericalregs by end of the year • http://ostseis.anl.gov/

  20. Overland Pass Pipeline • 153-mile pipeline from southwest of Meeker, Colo., to east of Wamsutter, Wyo. • 14-inch pipeline to transport natural gas liquids • EA released this summer, comment period closed in August

  21. Little Snake: 26 APDs in FY 08 • JW Operating Company 1 • Julander Energy 1 • Merrion Oil and Gas 2 • New Frontier Energy 6 • Pioneer Natural Resources 3 • Samson Resources Company 1 • Wexpro Company 10 • Yates Petroleum 2

  22. Little Snake: RMP revision • Expect 45-day public comment period on add’l air analysis this month • Expect Record of Decision in 2009

  23. Little Snake: Hiawatha • Questar and WexPro propose up to 4,207 new wells in existing fields in CO & WY • Expect Draft EIS in November, 90-day comment period with public meetings

  24. Kremmling APDs • 2 APDs approved for EOG • About 15 pending total for multiple companies

  25. Solar Energy PEIS Draft out in Spring 2009 Public meetings, 90-day comment period

  26. Oil and Gas Lease Sale Next lease sale November 14 Public notice out next week

  27. More info www.blm.gov

More Related