Broadwind Wind Tower Shipments 2014. Pete Lynch/Dawn Johnston representing WisDOT Feb 26, 2014 – Northcentral Technical College. Overview. Project Description Routes Load Dimensions Known construction/Mitigations Communication Protocol Questions. Project Overview.
E N D
Broadwind Wind Tower Shipments 2014 Pete Lynch/Dawn Johnston representing WisDOT Feb 26, 2014 –Northcentral Technical College
Overview Project Description Routes Load Dimensions Known construction/Mitigations Communication Protocol Questions
Project Overview 256 loads - 64 four piece towers Projected Start - June 9 2014 Projected Duration - 8 to 10 weeks* * Depends on final loading plans/equipment rotation
Routes • Monthly operations calls to build and clear routes • 30 days prior to first move switch to weekly check in calls • LCS entries need to be timely and accurate • Monitored for incidents by central office • Monitored by region for program/project changes • Construction, Maintenance, Bridge Postings, etc
Routes (cont.) Map
Load Dimensions • All 15’6” H or less and 14’9” W or less • TOP – 220K wtg 180 L • Upper Mid – 245K wtg 185 L • Lower Mid – 258 wtg 180 L • Base – 258 wtg 150 L
Construction • STH 29 • June/July • Structures • B37-02-01 • B37-02-02 • Single Lane Closures • 14’ restriction 1 foot shy • STH 29 • July-Sept • Structures • B37-01-14 • Single Lane Closures • 14’ restriction 1 foot shy
Mitigation Sign Sleeve
Mitigation Sign Sleeve
Communication Protocol Dan Mulder Section Chief Freight and Roadside Facilities daniel.mulder@dot.wi.gov (608) 266-3471 Region OSOW staff can contact BHM Staff as well