1-Phase Padmounted Transformer Loading Analysis using Smart Meters. Michael L. Dyer P.E. Executive Engineer SRP. What we did. Twenty-five (25) REX 2 AGI nodes were installed in single phase padmounted transformers recording ( kWh & kVAh ) at fifteen (15) minute intervals

homer
Download Presentation

1-Phase Padmounted Transformer Loading Analysis using Smart Meters

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 1-Phase PadmountedTransformer Loading Analysisusing Smart Meters Michael L. Dyer P.E. Executive Engineer SRP

  2. What we did • Twenty-five (25) REX 2 AGI nodes were installed in single phase padmountedtransformers recording (kWh & kVAh) at fifteen (15) minute intervals • Selected transformers served single family houses • Variability: • Initial installation dates ranged from 1978 to 2006 • Number of connected loads ranged from 2 to 14 • Each of the load meters were also REX meters • The kWh & kVAh data also allowed determination of the load power factor • Thermal models using IEEE std. C57.91 were conducted using the interval meter data for system peak day • County assessor’s office records determined the house size • The maximum and minimum house size was used in our single phase sizing program to determine the recommended transformer size • If the sizing program indicated a different size than existed a thermal model was created for the recommended design size • Certified loss data was used for existing transformers, if not available, data from like vintage was used • Loss data for a recommended unit based on present purchase

  3. Our Single Phase Sizing Program Assumed House Size to be Served= 0.8[(Max.Size+Min.Size)/2)] + 0.2(Max.Size) Where Size is 1000Ft2 Assumed Load= 4.5(Assumed Size) For assumed sizes <4000Ft2 5.85(Assumed Size) For assumed sizes >=4000Ft2 Recommended Transformer Size <= (Assumed Load*Number of Loads*Coincident Factor)/1.19

  4. 7 July 2012