60 likes | 189 Views
TOB sensor quality. Regina Demina University of Rochester. Outline. Stability of IV Leaky strips. IV vs time. 3/61 failed on retest. 17/250 failed on retest. Current at 400V FNAL remeasurement vs DB. 0/65 failed on retest. IVCV no vacuum effect so far.
E N D
TOB sensor quality Regina Demina University of Rochester
Outline • Stability of IV • Leaky strips
IV vs time 3/61 failed on retest 17/250 failed on retest Current at 400V FNAL remeasurement vs DB 0/65 failed on retest
IVCV no vacuum effect so far Sensor left on chuck for several hours between measurements 1 and 2. Just needed rest?
Summary • Some instability of I leak vs time is observed • 2002 sensors seem to be the worst, fraction of originally passed sensors failing retests –6.8% • 2003 sensors look better (but maybe not enough time) • I leak increase seems to be related to leaky strip development