Flats Sequencing System Update MTAC January 30, 2008. Agenda. Deployment Change Dulles Pre-Production Operation FSS Track Update. Phase 1 Deployment. 29 Districts 33 Processing Facilities (FSS Locations) 28 Existing Processing Centers 5 New Facility Project (Integrated FSS Space)
E N D
Agenda • Deployment Change • Dulles Pre-Production Operation • FSS Track Update
Phase 1 Deployment • 29 Districts • 33 Processing Facilities (FSS Locations) • 28 Existing Processing Centers • 5 New Facility Project (Integrated FSS Space) • 2 - 5 Systems per Facility • 1,500 Zones, or more
Dulles Pre-production Status • Install Complete Oct 2007 • Integration/ Machine Testing Nov 2007 • Employee Training Nov 2007 • Live Mail Ramp-up Dec 2007 • Field Pre-Test/Test Feb 2008 • Full Machine Ramp Up Mar 2008
Dulles Live Mail Ramp-up • Reston VA, Zones 20190 and 20194 Started December 4th • December Low Flat Volumes • Runs Have Exceeded 40K • Taking DPS Flats to the Street • Fairfax VA, Zones 22030 Started Jan 22nd • Runs Have Exceeded 40K • Taking DPS Flats to the Street Testing and Ongoing Zone Ramp-up in February
FSS Track Update • Workgroup #115 • Mail Prep & Entry FSS Environment • Workgroup #119 • FSS Communications