1 / 7

Southern California Gas Company Marco Tachiquin Project Manager - DIMP (626) 319-0629

AGA Distribution Best Practices Program Leak Management Potential Roundtable Executive Presentation. Southern California Gas Company Marco Tachiquin Project Manager - DIMP (626) 319-0629 Mtachiquin@SempraUtilities.com. Company Background. Number of Customers 5,497,290 Miles of Main

hu-williams
Download Presentation

Southern California Gas Company Marco Tachiquin Project Manager - DIMP (626) 319-0629

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AGA Distribution Best Practices ProgramLeak ManagementPotential Roundtable Executive Presentation Southern California Gas Company Marco Tachiquin Project Manager - DIMP (626) 319-0629 Mtachiquin@SempraUtilities.com

  2. Company Background Number of Customers 5,497,290 Miles of Main 48,868 Number of Services 4,359,727 Number of Employees 7,136

  3. Leak Management Unique Processes • Distribution Risk Evaluation and Monitoring System (DREAMS), started in 2007, implemented in 2008 • Systematic approach to segmenting and risk-ranking mains & services • Steel, not under CP • PE installed prior to 1986 • All PE with Integrity Relevant Leak History • Pre-assessment work to define segments • Material, Size, Vintage, Environment, Business Districts • Corrosion leaks eliminated as a result of strategic replacements of worst performing mains & services • DREAMS interface with new GIS system and regulatory requirements • Over $37.5MM (Direct) annual expense on replacement work; 315,000-ft (2010 data)

  4. Highlights that would be included in roundtable presentations • Special Surveys • Increased leak surveys on segments that are scheduled for replacement but deferred due to resource allocations • Procedures for associating leak records to main segments and services. How we utilize knowledge of pipeline condition to manage leak probabilities and O&M activities.

  5. Leak Management Challenges • SCG Does not report all above ground leaks • MSA’s, Regulator Stations or M&R Facilities • DIMP Regulations will require reporting in the future • Increased Leak Survey of DOT Transmission Lines as a result of incidents in California (Bi-monthly on specific segments) • Leak Survey maps on grid maps versus optimized in GIS.

  6. Conclusion • Why you believe other companies can learn from your experiences/processes • Material Control • Rigid control of materials • Material evaluation process is tight • Material QA process • Risk Evaluation & Monitoring System (DREAMS) • Evolved automated system for risk ranking mains & services • Effective field procedures and training

  7. Questions