1 / 7

GLAST Large Area Telescope: Status of Tracker EM Testing Engineering Meeting December 9, 2003

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Status of Tracker EM Testing Engineering Meeting December 9, 2003 Robert Johnson Santa Cruz Institute for Particle Physics University of California at Santa Cruz Tracker Subsystem Manager rjohnson@scipp.ucsc.edu.

hubert
Download Presentation

GLAST Large Area Telescope: Status of Tracker EM Testing Engineering Meeting December 9, 2003

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Status of Tracker EM Testing Engineering Meeting December 9, 2003 Robert Johnson Santa Cruz Institute for Particle Physics University of California at Santa Cruz Tracker Subsystem Manager rjohnson@scipp.ucsc.edu

  2. Status of Tracker EM Testing • Thermal-Vacuum test: • Jack has edited the T/V test plan, but it is still riddled with TBDs. • Jack Goodman and Tom McCarthy are in Italy this week to firm up the details of the plan and understand the temperature control in the Alenia chamber. • Vibration Test—series of engineering working meetings this week • Torque loss in the corner flexures was understood qualitatively: • The torque spec was low, and no locking feature was used. • The design relied upon friction to prevent movement by up to 4 mils within the tolerance between flexure and shoulder bolt, which could have started the loss of preload. • Without tight support of the shoulder in the aluminum Grid, there was a potential for excessive bending stress on the bolt, which could have released the preload.

  3. Status of Tracker EM Testing • Resolution: • Revise the design to ensure that the joint really behaves as a shear pin, as it was modeled, with no reliance on friction to hold the shear. • Avoid high tolerance requirements for the Grid and flexure machining, but also avoid preloading stress back into the bottom tray. • Introduce a locking feature for the bolts. • SLAC concept (see drawings on the next page) • Corner flexures: conical bushing self centers in the flexure • Requires good precision on those 4 holes, matching TKR & Grid, to avoid preloading stress into the bottom tray. • The bushing will fit tight into the flexure and Grid to act as a shear pin. It will be easy to get the bolt started in the threads. • Side flexures: use an epoxy bushing (à la the Cal) to hold the shear load with essentially no alignment requirement.

  4. TKR Flexure Shoulder Bolt Grid Collar/Pin with conical head (pressed in) Corner-Flexure-Grid Attachment Concept under study at SLAC, down-selected from 4 different proposals. Steel conical bushing self centers in the flexure and carries the shear load, with a tight fit in the Grid. The bolt just holds it in place. Martin’s first cut at the dimensions:

  5. Grid Flexure Proposed Bracket Corner-Flexure-Grid Attachment • Sandro has proposed an extra bracket to be added to fix the flexure to the grid. Some issues to consider with this: • Clearance inside the grid (e.g. calorimeter & TKR cables) • Precision location of the 4 new holes (a friction mount won’t be accepted, so at least some of those holes will need shear pins).

  6. Other Work in Progress • The EM tower was removed from the damaged vibration fixture and mounted on a new one, where it is being tested in Pisa with a very low level acoustic stimulus (ESPI system). • No damage was seen to the helicoil inserts in the old fixture. • Confirmed that only 2 of the 8 side-flexure bolts lost a slight amount of torque, despite completion of the full-level lateral vibration with all corner flexures disconnected. • Work is under way at SLAC to procure and test 120-degree countersink screws to spread the load on the sidewalls and allow higher torque to be used there without damage to the carbon fiber. • This is only a potential issue–none of these screws lost torque in the test. • Other possibilities being considered to resolve this issue: • Shimming the closeout inserts during assembly. • Using inserts on all sidewall holes.

  7. Prognosis • MRB by Friday or Monday. • Complete all design work before the holiday. • CAD design of interface by Dec 11. • Incorporate into the Tracker flight drawings and IDD by Dec 15. • Retrofit the existing bottom-tray flexures and the vibration fixture in early January. • Get back on the vibration tester at Alenia as early as January 19. • The thermal vacuum test should follow the vibration, as we cannot run the vibration test with the thermocouples installed between trays.

More Related