An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 Persis S. Drell Stanford Linear Accelerator Center LAT Deputy Project Manager persis@slac.standford.edu 650-926-8791

  2. Outline • Technical Status- last month’s accomplishments • Issues identified and closure plans • Status of flight hardware • Cost and Schedule Status • Tower A Schedule • Delivery schedule for Tower B—Tower 16

  3. Accomplishments and Issues Identified in Tower A Fabrication • Tracker Tray Fabrication • Bias circuit bonding problem resolved • MRB 10/1/04 • Flight tray production restarted 10/4/04 • Tray Production Status (Plyform + INFN) • >90 bare trays (no converter or bias circuits) produced • Converter production • Tiles for Tower A at Plyform etched in Turin, primed in Plyform • Tiles for Tower B and beyond being etched and primed at GSFC • Delivery rate plan of 300 tiles/week • 21 trays completed with converter and bias circuit through T/V • 1 failure • 2 tiles had primer delaminate from converter foils (Turin process) • Cause under investigation • 3 others show bubbles (before T/V) • Disposition under discussion

  4. FLIGHT TRAYS SUMMARY Production Step Qty-FH Bare Panel 73 ESPI done 56 Panel with payload 20 T-VAC done 10 Tray Production Status (example)

  5. Issues Identified in Tower A Fabrication • Tower A Tray Assembly Status (G&A) • Anomaly found in assembly: missing connections on MCM • WORK IS STOPPED • 1 tray with MCMs bonded (but no SSDs yet) found to have a problem with no bias from the MCM to the two center ladder attachment points on the bias circuit. • One caused by resistor badly soldered on MCM • Cause of other is not yet known • 6 more MCMs of 32 tested in Pisa have at least 1 missing bias or HV connection • 18+ tested at SLAC do not show any problem • Currently applying all available resources in Pisa and at SLAC to determine root cause • G&A work is ~ 1 week behind nominal Tower A fabrication schedule at this point

  6. MCM and Bias Circuit

  7. Issues Identified in Tower A Fabrication • Other Issues for Tower A • In Tower 0, identified interference between connector on MCM and sidewall on many trays • New MCM bonding procedures finalized to ensure connector stay clear • Critical hardware for Tower A assembly in work • Impacted by SLAC shutdown • Pulled work from shops and sent outside to complete • Flight cables for Tower A a critical problem

  8. Issues Identified in Flight Cable Production • Two technical issues identified: • Separations between barrel plating and internal layers. • Bubbles in adhesive holding connector to cable

  9. Path forward with Tracker Flex Cables • Parlex • CAP developed for plating process • Early tests validated new process • Coupon tests on cables with new plating process so far test acceptable • Process problems in cable assembly under discussion • Bubbles in the adhesive between the flex and the Omnetics connectors. • Stop work issued—QA visit tomorrow supported by tracker personnel • Delivery schedule continues to be unreliable • Project Manager to visit next week • Option: If new process has good coupons, consider getting bare cables and assemble at company of our choosing • Investigations underway • Current proposal to install cables in hand (with original plating process or with adhesive bubbles) if necessary to stay on schedule for Tower A assembly • Tower A will have lien to be resolved at a later time

  10. Alternate sources for tracker flex cables • Developing alternate source for full length cables • PO at Titan with 12/1 delivery to produce 5 C4 cables • Will proceed with QA source inspection if looks viable • Developing option of 2 short cables with ‘rigid-flex’ joint • Need to validate design • New drawings in process • Anticipate flight order with alternate source by 12/15

  11. Alternate sources for tracker flex cables

  12. Issues Identified in MCM Production • 343 units delivered to SLAC • 325 through burn in and final test at SLAC • Need 686 for 18 towers + electronics group • Production at Teledyne currently stopped • MCM Issues • Pitch adaptor • 13.5% drop out at MIP 1 due to broken traces (visual inspection) • Brittle Ni plating cracks easily in bend region, sometimes also cracking Cu • Two new pitch adaptor concepts in work to eliminate problem • Option 1: masking over bend radius • Option 2: selective plating process for Ni plating • New designs to be qualified when production at Teledyne resumes (scheduled for 11/15) • New electrical test fixture in test for detecting broken traces

  13. Issues Identified in MCM Production • MCM Issues (cont.) • MCM Leakage Current Problem • 8 boards have developed low resistance between layers 7 and 8 (120 V potential difference) of the multilayer board during burn-in. • Destructive Physical Analysis in process at Goddard and CALCE to determine root cause • Moisture during lamination or reflow, contamination, and conductive filament growth are all possibilities. • In case it is moisture, a pre-reflow bake has been added. Prepreg will be vacuum dried if more PWBs are made. • The problems seem clustered, so we are holding PWBs from the same panels as failed boards • The MCMs failed 2, 3.5, 4, 6, 10, 20, and 75 hours into our 168 hour burn-in where about 350 others did not fail giving hope that the burn-in catches almost all the problems. • Data readback errors • Some MCMs are too sensitive to clock duty factor during burn-in • Related to quality of clock received by GTRC • Problem mitigated by changing termination resistor on cables

  14. Issues Identified in MCM Production • MCM Conformal Coating Problems • Issues identified in QA with peeling, contamination and bubbles • A full inspection of all units has been completed. • CC got into many connectors. • They will be carefully cleaned • CC is lifting in small areas near components. • 200 thermal cycles did not make the lifting worse. • 3 vacuum cycles on 4 MCMs did not make lifting worse • The risk involved in reworking them may be greater than in using them as is. • CC is thin or missing on sides of many components • Due to spraying from only one direction • Mostly on non-conductive sides of “tall” components • Not clear if rework is practical. (CC could end up too thick.) • MRB 10AM 11/3/04 • In parallel, manufacturing process is being improved to prevent these problems on future units.

  15. Issues Identified in MCM Production • Restart of MCM Flight Production • Need improved ESD and PWB bake-out • Waiting for final quote • Implement conformal coat process improvments • Pitch adapter re-qualification program • MC restart MRR at Teledyne anticipated 11/15/04

  16. Flight Hardware Drawings Status • Top/Bottom Tray Panels (including flexures) • All drawings complete and released. • Interface Hardware • All complete and released. • Mid Tray Panels • Some rework and improvements of the drawings to reflect as-built condition are in work. • Tray Assembly (Bonding MCMs + Ladders to tray panels) • All complete and released. • Sidewall Drawings • All complete and released. • Heat Straps • Complete and released.

  17. Flight Hardware Drawings Status • Flex-Circuit Cables • All complete and released. Drawing revision to match as built in progress • Top Mount Cable Retainer and Alignment Hardware • All complete and released. • Tower Assembly Drawing • Complete and in release cycle • Electronics, including SSDs, MCMs, Bias Circuits, ASICs, etc.: all complete and released. • Ladder drawing revised to match as built. • Ready for release

  18. Status of Parts & Materials from SLAC

  19. Status of Parts & Materials from SLAC

  20. Status of Parts & Materials from SLAC

  21. Status of GSE from SLAC

  22. Status of GSE from SLAC

  23. Status of GSE from SLAC

  24. PMCS Schedule & Cost Variance • September: Schedule variance decreased from -$736k to -$575k on total $15,274 BCWI • Schedule has actually degraded due to work stoppage at Teledyne • Improvement in PMCS comes from receiving prepreg used for sidewalls • Keep in mind most of Tracker assembly work is in Italy and not tracked by this schedule variance calculation • Cumulative Cost Variance: -$456k • Large payment made to Teledyne for MCM’s received before work stoppage

  25. Schedule Status: Tower A Campaign • The Tracker team is focused on delivery of Tower A to I&T • Updated plan: Tower A ships 12/16/04

  26. Schedule Status: Tower Delivery Schedule • Updated plan: • Start production 10/4 • Plyform produces 4 trays/day starting 11/1 • G&A going to 2 shifts • Extra CMM • Extra Wire bonder • Tower 13,14 arrive in May