Information Standards Development Methodology (ISDM) Developer Training Day. March 2010. Section One. Information Standards. Benefits. Types. Method – Seven Stages. Current Situation. Why?. Transparency Choice Learn from mistakes Increase success Reduce costs & time.
E N D
Information Standards Development Methodology (ISDM)Developer Training Day March 2010
Why? • Transparency • Choice • Learn from mistakes • Increase success • Reduce costs & time
What • Stages • Process • Responsibilities • Products • Assurance Criteria
Need Stage Need Development Approach Statement of Need Research
Requirement Stage Requirements Requirement
Requirement Stage Requirements Analysis of Costs Requirement
Requirement Stage Requirements Analysis of Costs Test Strategy Requirement
Requirement Stage Requirements Analysis of Costs Test Strategy Implementation Strategy Requirement
Requirement Stage Requirements Analysis of Costs Test Strategy Implementation Strategy Maintenance Strategy Requirement
Requirement Stage Requirements Analysis of Costs Test Strategy Implementation Strategy Maintenance Strategy Advance Notification Requirement
Requirement Stage Requirements Analysis of Costs Test Strategy Implementation Strategy Maintenance Strategy Advance Notification Risk & Issues log Requirement
Board Decision Requirement Approved
Outputs from Requirement Requirement Requirements Test Strategy Implementation Strategy Maintenance Strategy IPLG approval Risk & Issues log Output from Requirement Scope & purpose clearly defined To cover end to end solution Concept of operation Process for maintenance and retirement
Difference from current practice • Formal Information Professional Leadership Group (IPLG) approval • (Fit with Operating Framework and fully resourced etc) • More rigorous adherence to submission products prior to formal approval • Documented and evolving quality criteria for each product according to ‘standard class’ • Greater emphasis on testing approach with formal piloting deferred to Full Standard
Draft Stage Specification Draft • Background • Purpose & scope • Customer need • Definition of standard • Technical architecture • Concept of operation- How it will be used • Testing to indicate the standard is being used properly – Conformance criteria • Related standards and interdependencies • Known Issues • Supporting information – Implementation and User guidance
Draft Stage Draft Specification Test Report • Summary of Testing purpose & method • Narrative of the testing process • Test results • Outcome of testing – Decision to proceed or not based on test criteria • Risk and Issues log
Draft Stage Draft Specification Test Report Clinical Safety Case • As agreed by Clinical Safety Group
Draft Stage Draft Specification Test Report Clinical Safety Case Implementation Plan • Scope of implementation - Technical, Organisational and Human Behavioural. • Funding and fit with National strategy • Clinical safety & IG implications • Conformance criteria • Migration strategy • Implementation timetable
Draft Stage Maintenance Plan Maintenance Plan Draft Specification Test Report Clinical Safety Case Implementation Plan • Maintenance organisation • Funding • Process and criteria for managing change • Release management & Version control • Risks and Issues log
Draft Stage Maintenance Plan Maintenance Plan Risks & Issues log Draft Specification Test Report Clinical Safety Case Implementation Plan • Key Risks & Issues presented to Board • Standard • Patients/clients • Users
Board Decision Draft Approved
Full Stage Full First of Type Implementation Report
Full Stage Full First of Type Implementation Report Specification
Full Stage Full First of Type Implementation Report Information Standards Notice (ISN) Specification
Full Stage Full First of Type Implementation Report Information Standards Notice (ISN) Specification Risk & Issues log
Board Decision Full Approved
Implementation Stage Risks & Issues log Post Implementation Review Implementation