Modification 175 – Solution Summary

UNC Review Group 175 – Encouraging Participation in the Elective Daily Metered Regime 26 th June 2008. Modification 175 – Solution Summary. Key aspects of the Solution Proposed: Tactical Solution based upon existing DM business rules, analysed against defined volume tranches

ianv
Download Presentation

Modification 175 – Solution Summary

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UNC Review Group 175 – Encouraging Participation in the Elective Daily Metered Regime26th June 2008

  2. Modification 175 – Solution Summary • Key aspects of the Solution Proposed: • Tactical Solution based upon existing DM business rules, analysed against defined volume tranches • Substantially follows the same UNC rules as for existing DM population • Sites nominated as DM Elective will be subject to Daily Read Provision by Shippers • Nominated sites will be treated the same as mandatory DM for the purposes of Settlement, including Reconciliation and Adjustment Processes • Minimise SPA Impacts on Shippers

  3. Modification 175 – Scope • Scope: • DM Elective market shall not include sites where the Supply Meter Point AQ is in excess of 58.6 GWh. • DM Elective market shall not include Interruptible meter points. • DM Elective market shall not include Unique Sites. • Meter points with an AQ greater than 73,200kWh may elect to be DM. Market Sector Code shall not be relevant. • Prime and Sub meter points may elect to become DM. • Where a meter point elects to become DM and is part of Prime and Sub metering arrangement, it is not required that all meter points within such configuration become DM Elective. • The DM Elective service response provided by xoserve includes only Supply Meter Points directly connected to the Large Transporters Distribution Networks.

  4. DM Elective Service • Following the implementation of UKL Technology refresh capacity does now exist to enable growth in the daily read market • Immediate growth up to 25,000 supply points - with a potential to continue through to 50,000 following initial stage system and process performance monitoring. • Within day (&D+5) activities associated with incorrect consumptions, failed reads and resynch visits carry high operational overhead. • Utilising DM Mandatory processes as a tactical solution has its limits and inefficiencies for a growing AMR market. • AMR failure rates are a key factor in determining the operational overhead and therefore ongoing costs, or case for investment in process enhancement / strategic solution • Existing DM reconciliation rules result in a complex settlement regime (Energy & Transportation) with high data and validation dependency

  5. Modification 175 – Next Steps • Confirmation of Business Rules and Assumptions • Complexity of System Change requires formal analysis and engagement with ODC / Infrastructure Provider. • Undertake analysis based upon defined Business Rules and identified processes, to define: • Cost of Change • Cost to Operate • Confirm Process Capacity Assumptions • Assess Feasibility and Costs against Volume Tranches

  6. Appendix – Detailed Business Rules

  7. Modification 175 – Business Rules • Where a Supply Meter Point no longer meets the criteria of a DM Mandatory Supply Meter Point the shipper may elect to reconfirm such meter points as DM Elective or NDM. • Where such meter points remain read by DMSP, these shall be DM Voluntary Meter Point. • Where a DM Elective Supply Meter Point meets the criteria of a DM Mandatory Supply Meter Point the shipper MUST reconfirm as DM Mandatory. • Where a DM Voluntary Meter Point is nominated as DM Elective, any future change back to DM Mandatory will incur Logger Installation Charges for relevant Shipper.

  8. Modification 175 – Treatment of Readings - Business Rules for Base Level Service • Readings from DM Mandatory meter points shall continue to be provided by DMSPs within the same timescales as currently. • Readings for DM Elective supply meter points will be submitted via I’X by Shippers. • DM Elective Readings must be received within file by [10am] so that downstream processes are not impacted. • DM Elective Readings file can only contain Actual Readings. • Validation of Readings within this file shall be performed by Shippers prior to submission. • Sense check validation (e.g. number of dials) will be applied by xoserve. • UNC Validation Rules shall be applied by xoserve. • Where an acceptable Actual Reading is not provided, xoserve shall generate an Estimated Reading. This reading shall be charged to the Shipper.

  9. Modification 175 – Treatment of Readings - Business Rules • Where an Estimated Reading is loaded this may be replaced by a Shipper provided Actual Reading up to D+5. The Estimated Reading shall remain chargeable. • Where an Actual Reading is provided this cannot be replaced by a subsequent Actual Reading. • Provision of Actual readings by 11.00am to Shippers will not be required. Consequently, the existing liabilities are not relevant. • An Annual Physical Check Reading is mandatory. A new process to obtain such readings is required when readings are not notified to xoserve.

  10. Modification 175 – Issues for Wider Consultation • Treatment of remaining NDM sites where a satisfactory statistical profile cannot be derived for Demand Estimation within the relevant End User Category. • Treatment of Reconciliation – Amended Suppression Criteria - Impacts on other Market Sectors. • Reconciliation of Prime and Sub meter points where DM Elective meter points are included within the configuration. Currently all meter points within a P&S configuration are to be read by the same party.

  11. Modification 175 – Assumptions • DM Elective meter points will be identified via SPA Processes as DM Elective. • DM Elective meter points shall be subject to ratchets. • Only NDM Supply Points shall be subject to Rolling AQ Review. Once a site is classified as DM – either as Elective or Mandatory - this will be subject to annual review only. • DM Elective remote reading equipment data shall not be stored or maintained by xoserve on UKLink systems.

  12. Modification 175 – System Changes Identified • Provision Reading Process • Setting the Resynchronisation Flag • Supply Point Administration Processes • Identification of DM Elective Sites • Reconciliation and Adjustment Invoicing • Assessment of Amended Suppression Criteria

  13. Modification 175 – Further Processes Identified • Existing DM Processes: • Input of the Annual Check Visit Date • Input Resynchronisation Readings • Input Resynchronisation Volume and Rollover Value • Valid Zeroes Flagging • Offline Consumption Adjustments • Flag Datalogger Faults • Reconciliation of Estimates between Actuals • New Processes to be defined: • Definition of Must Check Visit and Invoicing • Invoice for the Provision of Estimates • Notification of DM Elective / DM Mandatory switches to Networks