RFP# 99FY12 Ashlawn ES/Williamsburg ES June 8, 2012. Need for More Capacity. Driven by increases in enrollment system-wide 18% increase in enrollment in 5 years 83 relocatable classrooms in place today Additional relocatables this summer
E N D
RFP# 99FY12 Ashlawn ES/Williamsburg ES June 8, 2012
Need for More Capacity • Driven by increases in enrollment system-wide • 18% increase in enrollment in 5 years • 83 relocatable classrooms in place today • Additional relocatables this summer • Continued growth in number of births and County population and changing housing market suggest increases will continue for the foreseeable future
ProjectedCapacity Deficit + Capacity numbers do not include relocatable capacity. *Enrollment numbers do not include some alternative education programs.
Capacity Planning Process Goals • Respond to increasing enrollment by adding permanent building capacity to APS as part of the Capital Improvement Plan • Achieve the plan for additional seats through a transparent, structured, and inclusive process
School Board Evaluation Criteria Optimize Impact on Capacity • Flexibility of the solution • Larger impact of the solution • Increase number of seats at schools with specific admission policies • Number of seats generated • Relieving crowding in schools of critical capacity need Minimize Variation from Preferred School Size • Maintain preferred seat range Neighborhood Resources • Impact on playgrounds • Impact on playfields • Impact on parking • Impact on green space • Neighborhood impact Optimize Operational Effectiveness • Minimize administrative impact • Equity of space utilization • Impact on transportation structure
Community Outreach – To Date • 8 Civic Associations • 8 PTA Meetings • 5 School Board Work Sessions • 5 Community Updates • Various Staff, County, & Citizen Meetings • Evaluation Committee • Facilities Advisory Council & PCS • Public Facilities Review Committee 9
Community Outreach – Future BLPC APS Building Level Planning Committee PFRC Arlington County Public Facilities Review Committee 10
All APS/ Select County Sites CAPITAL IMPROVEMENT PLAN
Ten-Year CIP • Ten-year CIP totals $538 million • Adds approximately 4,800 new seats (2/3 of projected capacity deficit) • Major Construction • Capital Reserve • Bonds • Minor Construction/Major Maintenance (MC/MM) • Current Revenues
CIP Years 1-5Opening of New Elementary Seats • School Opening Year (Fall) • 2014: 225 seats at Ashlawn • 2015: 600 seats at new neighborhood school (WMS campus) • 2016: 450 additional seats at McKinley & ATS • 2017: 600 seats at new choice school (CS/Kenmore campus)
CIP Years 6-10Additional Elementary Capacity • First projects achieve good balance of enrollment to capacity • Need to re-examine model criteria and re-score options based on new boundaries and utilization rates • Add’l 1,200 seats needed in years 6-10 • Funding needed to create 600 seats (locations TBD)
CIP Years 6-10Secondary Options • Develop robust list of secondary options (construction and non-building) • Re-examine criteria and rating scales for secondary capacity options • Continue to monitor growth and identify site options • Focus on secondary school building options in 2014 CIP/capacity planning process • Funding needed to create 2,300 seats (locations TBD)
Proposed Capacity Funding • 2012: $46.8M (1 addition; 1 new school) • 2014: $70.9M (2 additions; 1 new school) • 2016: • 2018: • 2020: $51 M Elementary 600 seats $127 M Middle 1,500 seats $63 M High 800 seats
Ten-Year CIP Funding • Major Construction • Capital Reserve funded • Ashlawn 12-Room Addition $14.9M • Williamsburg - new ES – design $ 4.0M
Ten-Year CIP Funding • Major Construction • Bond funded • Wakefield HS (2010 bond) $ 29.1M • Fiber Project/C-net (2010 bond) $ 0.3M • ATS 12-Room Addition $ 16.1M • McKinley 12-Room Addition $ 16.1M • Carlin Springs/Kenmore new ES $ 46.4M • Williamsburg - new ES – construction $ 39.1M • HVAC & Roofing (20-yr useful life) $ 34.6M • Infrastructure Projects (20-yr useful life) $ 21.0M • Capacity Projects – Years 6-10 $253.0M