Mu2e WGM. 5/2/2012 R. Ray Mu2e Project manager. Status. We have performed the second turn of the schedule crank ahead of schedule and are now producing reports. There is still a lot of checking and fixing to do, but we have made significant progress and are on track for the Lehman Review.
E N D
Mu2e WGM 5/2/2012 R. Ray Mu2e Project manager
Status • We have performed the second turn of the schedule crank ahead of schedule and are now producing reports. • There is still a lot of checking and fixing to do, but we have made significant progress and are on track for the Lehman Review. • We continue to receive very strong support from the Lab in providing much needed resources during this time. R. Ray - Mu2e WGM
Review Schedule R. Ray - Mu2e WGM
Resource Leveling R. Ray - Mu2e WGM
Project Schedule • CD-2/3a – March 2014 • Need to get CD-2 by 1st week of Feb 2014 to get construction funds in FY14. Must get CD-2 within 1 year of President’s FY14 budget request. • Director’s Review – Oct. 2013 • DOE Review – Nov. 13 (should probably be December) • Sign off – March 2014 • CD-3b – July 2015 • Key Performance Parameters achieved – August 2019 • CD-4 – January 2020 • CD-4 Milestone – February 2021 (18 months of float from KPPs) R. Ray - Mu2e WGM
Schedule CD-2/3a CD-1 CD-3b Preliminary Design Final Design Field Mapping Final Solenoid Design in Industry Fabricate Superconductor Solenoid Fabrication Solenoid Installation Operations Detector Hall Construction Solenoid Infrastructure Cosmic Ray Tests Detector Construction Install Detector Accelerator Common Projects FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 R. Ray - Mu2e WGM 6 6