Summary of the Workshop on Beam Instrument Upgrades and Consolidations

Summary of the Workshop on Beam Instrument Upgrades and Consolidations. Objectives. Get a common view and understanding of BI activities related to the Consolidation and Upgrade projects R eview the status of functional specifications

Download Presentation

Summary of the Workshop on Beam Instrument Upgrades and Consolidations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Summary of the Workshop on Beam • Instrument Upgrades and Consolidations • Objectives • Get a common view and understanding of BI activities related to the Consolidation and Upgrade projects • Review the status of functional specifications • Agree on priorities, plans and actions whenevernecessary • Agree on budget spending profiles or corresponding actions

  2. About budget #1 • We agreed that is not straightforward today to get a precise view on the spending profiles due to various reasons: • Some projects are funded partly between CONS and LIU • Some sources give the total figure per instrument over the entire project length • Some sources give spending profiles but for the entire BI package (EVM?)

  3. About budget #2 • It has been agreed that this situation has to be improved mainly in 2 directions: • Transfer Consolidation budgets towards LIU budgets for every item with budgets from both projects • Put in place and keep up-to-date a common overview, presenting spending profiles for each WU, as reference for all stakeholders • This work is in progress. It will have to be finished before October’s review, hopefully sooner. • →Action LIU management. • BI should provide up-to-date figures before 09/2012

  4. About specification #1 • Functional specification documents have been mentioned and briefly presented during the workshop: • One gathering the full machine parameter ranges to be covered after the upgrade • One functional specification per beam observable (i.e. intensity, losses, position, transverse size and tune)

  5. About specification #2 • The approval process has been discussed and we agreed that these documents will be introduced into EDMS and circulated for comments for a period of 2 weeks. • BI will then organize dedicated technical meetings per observable (covering the 3 machines) with the people involved in the approval process to finalise the documents. →Action BI

  6. Plan #1 • Decide on need for new transformer for 1000 turn measurements →Action BI-OP – 2012 • Investigate the possibility of scanning at 20 m/s with the existing wire scanners (with new motors, bellows and acceleration function) during LS1 →Action BI • For all machines, it has been agreed: • Prepare and send to EN/EL preliminary DICs for all projects requiring new cables before the end of May →Action BI

  7. Plan #2 • Prepare and send to TE/VSC before the end of May an exhaustive list of BI interventions required during LS1 →Action BI • Send a Memo to F. Bordry to inform him about the priorities (and risk associated) of the LIU project in terms of cabling campaign and vacuum interventions • Identify and test more suited acquisition systems for fast BLM observation on all machines →Action BI

  8. BI plan for the PS #1

  9. BI plan for the PS #2