An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Drive-Laser Commissioning Status and Plans • Recent Laser Milestones • Safety • Technical • Where do we stand today? • Laser Acceptance Status • Laser Commissioning • UV on cathode – Injector Commissioning

  2. Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006

  3. Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006

  4. Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006 EIP Checkout at Thales Factory

  5. Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006

  6. Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006

  7. Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006

  8. Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006

  9. Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006

  10. Safety Coming Up • LSS Hardware installation complete and certified Oct 27, 2006 • LSO Walkthrough Oct. 30, 2006 • Operation under Final SOP Oct 30, 2006 • Vault Laser Wall complete Nov 17 • Vault LSS Complete and Certified Nov 24, 2006

  11. Technical Milestones • July 14 – Laser Tables Installed

  12. Where are we now? - Recent Milestones • July 21 – Laser Arrives at Sector 20

  13. Where are we now? - Recent Milestones • July 24 – Complete system on table

  14. Where are we now? - Today • Laser Work • Complete LSS • Move laser supplies into rack • Setup streak camera • Setup cross-correlator • Setup UV-FROG • Setup spatial diagnostics Laser Infrastructure complete

  15. Where are we now? - Today Streak Camera installed and working

  16. Where are we now? - Today Cross-Correlator working

  17. Where are we now? - Today TG-FROG working

  18. What's Next - Laser Commissioning • Installation of shaping and transport to begin late-Oct or early-Nov • One week down for electrical and cable plant • Spatial shaper is in hand • Pointing stability lock system has been tested and is ready for installation • All other components are in hand

  19. What's Next - Laser Commissioning • Laser table and LSS in Vault • Laser door installed prior to transport – Nov 20 • Components will be installed and tested in laser bay prior to table moving to vault • Support for laser table should be ready for table installation on Nov 28th

  20. What's Next - Laser Commissioning • Virtual cathode work requires GTL. • Gun can be installed two weeks after GTL installation • UV on cathode one week later. • Laser optimization (temporal profile, stability, automation, etc) will continue until GTL is installed.

  21. End