210 likes | 226 Views
Drive-Laser Commissioning Status and Plans. Recent Laser Milestones Safety Technical Where do we stand today? Laser Acceptance Status Laser Commissioning UV on cathode – Injector Commissioning. Safety Milestones. SOP PDR Dec 16, 2005 SOC Review Feb 22, 2006 Thales ESC May 15, 2006
E N D
Drive-Laser Commissioning Status and Plans • Recent Laser Milestones • Safety • Technical • Where do we stand today? • Laser Acceptance Status • Laser Commissioning • UV on cathode – Injector Commissioning
Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006
Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006
Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006 EIP Checkout at Thales Factory
Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006
Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006
Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006
Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006
Safety Milestones • SOP PDR Dec 16, 2005 • SOC Review Feb 22, 2006 • Thales ESC May 15, 2006 • SOP FDR March 6 2006 • LSC Temp SOP May 9, 2006 • SOC Approved July 14 • LCLS Work Auth. July 19, 2006 • LSC Final SOP October 10, 2006
Safety Coming Up • LSS Hardware installation complete and certified Oct 27, 2006 • LSO Walkthrough Oct. 30, 2006 • Operation under Final SOP Oct 30, 2006 • Vault Laser Wall complete Nov 17 • Vault LSS Complete and Certified Nov 24, 2006
Technical Milestones • July 14 – Laser Tables Installed
Where are we now? - Recent Milestones • July 21 – Laser Arrives at Sector 20
Where are we now? - Recent Milestones • July 24 – Complete system on table
Where are we now? - Today • Laser Work • Complete LSS • Move laser supplies into rack • Setup streak camera • Setup cross-correlator • Setup UV-FROG • Setup spatial diagnostics Laser Infrastructure complete
Where are we now? - Today Streak Camera installed and working
Where are we now? - Today Cross-Correlator working
Where are we now? - Today TG-FROG working
What's Next - Laser Commissioning • Installation of shaping and transport to begin late-Oct or early-Nov • One week down for electrical and cable plant • Spatial shaper is in hand • Pointing stability lock system has been tested and is ready for installation • All other components are in hand
What's Next - Laser Commissioning • Laser table and LSS in Vault • Laser door installed prior to transport – Nov 20 • Components will be installed and tested in laser bay prior to table moving to vault • Support for laser table should be ready for table installation on Nov 28th
What's Next - Laser Commissioning • Virtual cathode work requires GTL. • Gun can be installed two weeks after GTL installation • UV on cathode one week later. • Laser optimization (temporal profile, stability, automation, etc) will continue until GTL is installed.