LSWT#4. Open Cruise Requirements status and planning. LSWT#4, Venice 30/03-01/04-2009. SCrOP Annex_G - PC10. Active Payload Checkout PC10: Regular tests for active checkouts ESS RAM Patch Test for ESS events Finalize SW Upload for Lander Units, Part 2 of 2: SW Upload for SESAME
E N D
LSWT#4 Open Cruise Requirements statusand planning LSWT#4, Venice 30/03-01/04-2009
SCrOP Annex_G - PC10 • Active Payload Checkout PC10: • Regular tests for active checkouts • ESS RAM Patch Test for ESS events • Finalize SW Upload for Lander Units, Part 2 of 2: • SW Upload for SESAME • SW Patch for ADS (tbc) • + COSAC SW Upload • + CIVA SW Upload • + APXS parameter setting, re-run PC8 test All units SW shall be final after PC10. This does not apply for CDMS: • SW8.0 upload PC12 • Lander internal Interference Tests (Part 1) • On-comet Preparation tests, Part 1 • New requirements from • PTOLEMY to finalize activities (substitute existing requirement) • CONSERT tests on switch-ON accuracy
SCrOP Annex_G - PC12 • Active Payload Checkout PC12: • CDMS SW Upload to V8.0 • Battery charge to 100% prior DSH • Regular tests for active checkouts • Contingency activities, if needed • S-D-L combined tests(mainly driven by Flywheel S-D-L operations) • Lander Internal Interference Tests, Part 2 • On-comet Preparation tests, Part 2(MUPUS, CONSERT) ANCHOR, COSAC, PTOLEMY, CONSERT
Cruise Phase Events 2009 • Passive PC9 Jan 2009 • PC9 execution -> Jan 2009 • Rosetta Thermal Characterization • Test execution -> Feb-2009 • Active PC10 • High level inputs to ESA -> Feb 2009 • Start of GRM campaign -> May 2009 • End of GRM campaign -> July 2009 • LOR delivery -> Aug 2009 • GO/NOGO -> 03-Sep-2009 • PC10 execution -> 21-Sep to 02-Oct 2009 • ESB3 (no Philae activities) • High level inputs to ESA -> Feb 2009 • ESB3 CA -> 13-Nov-2009
Cruise Phase Events 2009/2010 • In-flight Power System Test (PSS, MPPT, SBatt) • High level inputs to RMOC -> Nov 2009 (tbc) • End of GRM campaign -> Jan 2010 (tbc) • LOR delivery -> Feb 2010 (tbc) • PST execution -> February 2010 • CDMS SW V8.0 verification • Start -> September 2009 • End -> Nov 2009 • Active PC12 • High level inputs to ESA -> Oct 2009 • End of GRM campaign -> Feb 2010 • LOR delivery -> Mar 2010 • GO/NOGO -> Apr 2010 • PC12 execution -> April/May 2010
Cruise Phase Events 2009/2010 • Lutetia • High level inputs to ESA -> March 2009 • End of GRM campaign -> Apr 2010 • LOR delivery -> May 2010 • GO/NOGO -> June 2010 • LUT CA -> 10-July-2010 • Passive PC13 =>Last payload activity prior DSH!!! • PC Change Req. to ESA -> Sep 2010 • LOR delivery -> Oct 2010 • GO/NOGO -> Nov 2010 • PC13 execution -> Dec 2010
Cruise - OPS Preparation Schedule 2009 • PC10 EQM Test RMOC -> April 2009 • PC10 Start of GRM campgn -> May 2009 • PC10 End of GRM campgn -> July 2009 • PC10 LOR delivery -> Aug 2009 • PC10 GO/NOGO -> 03-Sep-2009 • CDMS SW8.0 Test Start -> September 2009 • PC10 execution -> 21-Sep to 02-Oct 2009 • PC12 First Inputs to ESA -> Oct 2009 • PST Inputs to RMOC -> Nov 2009 (tbc) • PC12 SCrOP + timeline -> Nov 2009 (tbc) • CDMS SW8.0 Test End -> Nov 2009
Cruise - OPS Preparation Schedule 2010 • PST GRM campgn -> Jan 2010 (tbc) • PST LOR delivery -> Feb 2010 (tbc) • PST execution -> February 2010 • PC12 End of GRM campgn -> Feb 2010 • PC12 LOR delivery -> Mar 2010 • PC12 GO/NOGO -> Apr 2010 • LUT End of GRM campgn -> Apr 2010 • PC12 execution -> April/May 2010 • LUT LOR delivery -> May 2010 • LUT GO/NOGO -> June 2010 • LUT CA -> 10-July-2010 • PC13 Change Req. to ESA -> Sep 2010 • PC13 LOR delivery -> Oct 2010 • PC13 GO/NOGO -> Nov 2010 • PC13 execution -> Dec 2010
Longterm planning • Deep Space Hibernation Phase (DSH) • Start DSH July 2011 • End DSH January 2014 • Payload Commissioning Period April/May 2014Limited Resources !!! (Power/Data) • Comet Phase Start August 2014 • Global Mapping 18-Aug to 21-Sep 2014 • Close Observation 22-Sep to 19-Oct 2014 • Lander Delivery Period Start October 2014 • Lander Delivery 11-Nov-2014 • Lander Baseline Mission 12 to 16- Nov2014 • Comet Escort Phase • Start Escort Phase 17-Nov-2014 • Perihelion 13-Aug-2015 • End Escort Phase 31-Dec-2015
Open NCR Status • Total of 28 open NCRs to units FM model: • APXS (1) ->PC10 ADS (2) ->PC10 • CIVA (3/1*) ->PC10 Battery* (1) • CONSERT (2) ->PC10 CDMS (10) ->PC12 • COSAC (1) ->PC10 ESS* (2) • PTOLEMY (1) ->PC10 PSS* (3) • ROMAP* (2) Last review based on dedicated emails and LOWG#12 presentations (*) further clarification required