Estimating your Cost of Production for Growing Irrigated Corn. Paul D. Mitchell Agricultural and Applied Economics UW-Madison and UW-Extension Hancock ARS February 1, 2006. Goal Today. Present basic cost concepts and methods to estimate cost of production
E N D
Estimating your Cost of Productionfor Growing Irrigated Corn Paul D. MitchellAgricultural and Applied Economics UW-Madison and UW-Extension Hancock ARS February 1, 2006
Goal Today • Present basic cost concepts and methods to estimate cost of production • Simple method to estimate a typical cost of production for a farm your size • Work through an example • Cost of Center Pivot Irrigation • Returns to Irrigated Corn
Major cost categoriesfor crop production • Variable Input Costs • Seed, fertilizer, herbicides • Machinery Costs • Fixed: depreciation, capital cost • Variable: maintenance, fuel, lubrication • Land, Labor, and Management • Often unpaid costs of your time and your management skill and energy
Variable Input Costs • Amount of each input times its price • Add them all up to get variable input costs • Simplified examples for corn • Seed: $110/bag x 0.425 bag/ac = $46.75/ac (80,000 seeds/bag, 34,000 seeds/ac) • Nitrogen: 200 lbs N/ac x $0.35/lbs = $70/ac • Prowl: 1.5 lbs/ac = $9.75/ac
Machinery Costs • Substantial component of costs (25-40%) • Difficult to measure/estimate: user specific • Variable Cost, Use-Related Cost, Operating Cost • Costs due to using the machinery • Fuel, lube, maintenance, use-related repairs and labor • Fixed Cost, Time-Related Cost, Overhead Cost • Costs paid whether you use the machinery or not • Interest, insurance, taxes, housing • Depreciation: both a variable and fixed cost
Machinery Costs • Best method: keep accurate records and use them to determine your actual costs • Estimate Costs • When do not have records, or want to compare costs for different options • Economic Engineering • Custom Rates
Economic Engineering Approach • Estimate machinery costs based on careful engineering data collection • Use the machinery and carefully document • repairs, maintenance, fuel/lubrication • speed, turning time, labor • Develop formulas to estimate fixed and variable machinery costs
Economic Engineering Approach • Farm Machinery Economic Cost Estimates for 2005, Lazarus and Selley at U of MN, Center for Farm Financial Management http://www.apec.umn.edu/faculty/wlazarus/mf2005.pdf • Numbers seem too low?
Machinery Cost Example • What does it cost to run a chisel plow? • Lazarus and Selley 2005 (23 ft): $6.81/ac • Iowa 2005 Custom Rate $11.05/ac • Wisconsin 2004: $13.30/ac • Indiana 2004 Custom Rate $11.78/ac • South Dakota (East) Custom Rate: $10/ac • Missouri 2003 Custom Rate $10/ac ($12.10/ac heavy soil) • SW Minnesota 2001: $10.83/ac
Economic Engineering Approach • Ron Shuler (UWEX/BSE): Updated A3510 “Estimating Ag. Field Machinery Costs” • Print copy with worksheets, spreadsheet • Estimate costs when no records • Recommends using actual data to determine your actual machinery costs
Why not just use Custom Rates? • Custom rates not good estimates of typical farmer costs—usually too low as well • Run over more acres, spread fixed costs • Volume discounts or search for best price, so lower purchase price • More efficient operators • Family/friends not charge enough • Discounted because not perfect timing
Converting Custom Ratesto your Cost • Adjusting custom rates is an easy way to estimate typical machinery costs • K. Dhuyvetter and T. Kastens at Kansas State University developed a formula using KFMA cost data and custom rates • Scale Factor = 1.241 + (33.026/acres) • Your Cost = Scale Factor x Custom Rate • Acres is annual acres operated
1.55 Acres Scale Factor 100 1.571 1.50 200 1.406 1.45 300 1.351 400 1.324 1.40 500 1.307 Scale Factor 600 1.296 1.35 700 1.288 1.30 800 1.282 900 1.278 1.25 1000 1.274 1.20 1100 1.271 0 500 1000 1500 2000 2500 3000 1200 1.269 Acres of Cropland 1300 1.266 1400 1.265 1500 1.263 1600 1.262 1700 1.260 1800 1.259 1900 1.258 2000 1.258 1 – Scale Factor = % increase (as decimal) that your costs exceed the Custom Rate
Caveats • Custom rates have wide ranges—call around, use WI publication and those from other states • Formula to adjust custom rates not perfect • Use these machinery costs as a guide, not gospel • Need good records to estimate your costs • Returns to land and Management does not include Farm Program payments • Government Payment Calculator at http://www.afpc.tamu.edu/ to estimate
Irrigation Summary SUMMARY ANNUAL OWNERSHIP COSTS $/irg ac Depreciation Pivot & Well $31.17 Interest/Opportunity Cost $51.80 Insurance $3.70 TOTAL ANNUAL OWNERSHIP COST $86.67 OPERATING COSTS $/irg ac Electric Power $29.68 Labor run/manage pivot $1.33 Maintenance $11.10 TOTAL ANNUAL OPERATING COST $42.11 TOTAL COST $128.78
SUMMARY $/ac Total Machinery Costs $101.99 Total Variable Input Costs $165.16 Total Irrigation Costs $128.78 Total Variable Harvest Costs $44.88 TOTAL COST $440.81 Average Yield (bu/ac) 220 Expected Price ($/bu) $2.00 Expected Revenue ($/ac) $440.00 Net Returns to Land & Management - $0.81 Irrigated Corn Summary
Summary • Can make money on irrigated field corn • Keep costs low (inputs, irrigation, machinery) • Get good price — good marketing • Crop insurance (GRP/GRIP + Hail) and forward pricing to remove some of the yield & price risk
Questions ??? Paul Mitchell Agricultural and Applied Economics UW-Madison and UW-Extension (608) 265-6514 pdmitchell@wisc.edu My Extension Homepage www.aae.wisc.edu/mitchell/extension.htm