An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Map of Current Water System (section relevant for EWB-MAP modifications)RED lines – supply lines to tank (uphill by pump)BLUE lines – distributions lines by gravity DOWNHILL

  2. Proposed update to Water System (section relevant for EWB-MAP modifications)RED lines – supply lines to tank (uphill by pump)BLUE lines – distributions lines by gravity A F NEW DISTRIBUTION LINE 2a NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b E DOWNHILL NEW DISTRIBUTION LINE 2c B NEW TANK C

  3. Piping System Layout New Pipelines Waypoints • Supply Line 1 to new tank (A-B-C) • Length = 365 m + tank connection (assume + 10 m) = 375 m • 1 bend, 1 tee, 3 elbow, 2 valves, 1 exit • 17 m elevation rise + tank height • Hill rises to 643 m then valley falls t0 640 m on connecting road (D-B) • ~175 gpmflowrate • Distribution line connection 2a from lower Tramo 3b to lower Tramo 6 (E-F) • 105 m length, elevation change unclear, guess 10 m drop • Distribution connection 2b from upper Tramo 3b to upper Tramo 6 (B-D) • 120 m length, 8 meter drop with low point at 640 m (3 m below D) • Distribution line 2c from new tank to new connections (C-B-E) • 255 m length, 11 meter elevation drop

  4. Proposed update to Water System (section relevant for EWB-MAP modifications)RED lines – supply lines to tank (uphill by pump)BLUE lines – distributions lines by gravity A 20 m DOWNHILL 240 m NEW SUPPLY LINE 1 B NEW TANK C 105 m

  5. Estimate of head losses in supply pipe 1 (smooth PVC) 4” PVC sufficient to keep major and minor losses to >10% of the elevation change

  6. Assumptions for Supply Pipe 1 Calculation

  7. Supply Pipe 1 Pipe Profile(not to scale) C 651 m 655 m B Elevation: 640 m 643 m 105 m 638 m D A 240 m 640 m 20 m Tee connect to 6” pipe Gate Valve 45° Elbow 90° Elbow Gate Valve 90° Elbow 90° Elbow Pipe Exit PIPE FITTINGS NEW TANK

  8. Supply Pipe 1 Trenching • Based on recommendations from EWB Water Resource Guidelines: • 45 cm trench depth • 10 cm bedding (2-12 mm soil) if stones/rocks present in trench • Back-fill with soil that is free of lumps, from stones (>3 cm), and from organic matter • PVC pipe joined in trench and cure for >10 hr prior to pressurizing. Keep joints exposed to check for leaks • For road crossing, bury PVC pipe inside steel or concrete pipe (ID > diameter of PVC joints) and bury at same depth as standard trench 45 cm trench depth 10 cm bedding

  9. Thrust Anchors for Elbows &Tees From Russ Turner, Tetratech

  10. Thrust Anchor Dimensions • Based on • 4” PVC PIPE • 45 cm Trench Depth • Height of Anchor • 22.5 cm • Length of Anchor Backing against undisturbed material: • 90° BEND: L = 83 cm • 45° BEND: L = 41 cm • Tee: L = 41 cm

  11. Supply Pipe 1 Materials List • 4” PVC pipe (Schedule 40) in 6 m lengths – 62 pieces • 4” PVC 45° Elbow – 1 piece • 4” PVC 90° Elbow – 1 piece • Tee connector & Adapter from 6” PVC main to 4” branch line – 1 piece • PVC primer, PVC cement, applicators, and cleanup • Gate/Ball valves (PVC or steel ?) – 2 pieces • 4” Steel Pipe (5 m) – 1 piece • 4” Steel 90° Elbow – 2 pieces • 4” PVC-Steel Pipe Connector – 1 piece • Bed material for trench (2-12 mm), if necessary • Fill material, if necessary • Concrete for Anchoring Piping at Bends • Concrete/Rebar for Valve boxes and lids • Tools for cutting, de-burring, connecting pipe

  12. EPA-NET Simulation for Supply Line 1 Matches Excel Calculations DOWNHILL

  13. DOWNHILL

  14. Summary of Existing Water System

  15. Modified water system

  16. Summary of changes in water distribution system CURRENT SYSTEM PROPOSED MODIFICATION Storage Tanque 1: 35,000 gal Tanque 2: 11,000 gal Tanque 3: 25,000 gal New Tank: 28,600 gal Old Pump supplies water to Tanques 1 & 3 at 175 gpm New pump supplies water to new tank at 175 gpm with much lower head Homes serviced by Tanques 154 33 117 New: 280 • Storage • Tanque 1: 35,000 gal • Tanque 2: 11,000 gal • Tanque 3: 25,000 gal • Pump supplies water to Tanques 1 & 3 at 175 gpm, ~3 days per week • Spring supplies water to Tanque 2 (and other tanques) • Homes serviced by Tanques • 291 • 33 • 260 New tank reduces demand of water from Tanques 1&2 (which require high head) by roughly 50%

  17. Current Water Distribution System 260 Homes Served by Tanque 3 291 Homes Served by Tanque 1 33 Homes Served by Tanque 2 DOWNHILL

  18. Proposed Water Distribution System 280 Homes Served by New Tank 117 Homes Served by Tanque 3 33 Homes Served by Tanque 2 154 Homes Served by Tanque 1 DOWNHILL