Upcoming Revision Overview ISO New England Ancillary Service Schedule 2 Business Procedure. Presented to The Transmission Committee April 28, 2010 Pete Harris – Manager, System Operations Support Jin Thian – Supervisor Monthly Markets, Settlements. Highlights. Drivers for change
E N D
Upcoming Revision OverviewISO New England Ancillary Service Schedule 2 Business Procedure Presented to The Transmission Committee April 28, 2010 Pete Harris – Manager, System Operations Support Jin Thian – Supervisor Monthly Markets, Settlements
Highlights • Drivers for change • Impacted Areas of the Schedule 2 Business Procedure • Desired Schedule • Next Steps
Drivers for change • Administrative Changes • Clean up old language that is no longer necessary • Consistency of terms • Provide clarifying language where appropriate • Address problems encountered in the Waiver Process
Impacted Areas of the Schedule 2 BP • Global Changes • Replaced the term Qualified Reactive Resource with QRR after its initial use • Removal of expired 01/01/09 AVR Requirements implementation date (this is now an on-going requirement) • Removal of sections related to expired transitional implementation language • 2.2.5.1 Added reference to following “voltage dispatch instructions” • 2.2.5.3 Added footnote allowing for the consideration of shorter test request submittal lead times • 2.2.5.5 Added clarification for testing of composite units
Impacted Areas of the Schedule 2 BP (cont.) • 2.2.6.2 Modified waiver process • 2.2.6.2.1 Added new section addressing waiver duration • 2.2.6.2.2 Added new section addressing a waiver’s impact on the NX12D data • 2.2.6.2.3 Modified waiver appeal requirements • Sections 3, 4 and 5 • Referenced Transmission, Markets & Services Tariff wherever applicable • Standardized language for Settlements-related procedures: LOC, CEC and CEP
Desired Schedule • 04/28/10 • Introductory Presentation to the Transmission Committee • 05/26/10 • Presentation of Red Line Changes to the Transmission Committee • 06/28/10 • Request a Vote of the Transmission Committee to recommend approval • 08/06/10 • Request approval of the Participants Committee
Questions For questions or concerns please contact • System Operations • Pete Harris - 413-535-4385 pharris@iso-ne.com • Settlements • Jin Thian – 413- 540-4464 jthian@iso-ne.com • Reliability and Operations Services • Bruce Kay – 413-535-4062 bkay@iso-ne.com • Legal • Monica Gonzalez – 413-535-4178 mgonzalez@iso-ne.com