90 likes | 254 Views
Managing Resource Utilization using Microsoft Project Leveling. Presented by Larry Christofaro, PMP, MCITP February 29, 2008. Introduction.
E N D
Managing Resource Utilization using Microsoft Project Leveling Presented by Larry Christofaro, PMP, MCITP February 29, 2008
Introduction • The process of rescheduling activities such that the requirement for resources on the project does not exceed resource limits. The project completion date may be delayed in the process. • Definition of “leveling” in Microsoft Project • Levels overallocated resources by delaying or splitting tasks • What are the ways you level projects today • How I started using Microsoft Project leveling
Managing Schedules • Progression of managing project timelines and resource utilization • One dimensional: Using tasks • Two dimensional: Using tasks and resources • Three dimensional: Using tasks and assignments • It takes managing with Microsoft Project leveling to get to level three • And yes, you need to have a pretty good idea of what it takes to manage a two dimensional plan.
Lets Build the Plan • Setup options (nothing needed) • Define tasks • Define resources • Assign resources to tasks
Microsoft Leveling Options • Microsoft levels using the following criteria • Standard: Dependencies, Slack time, Dates, Constraints, Priority • Priority/Standard: Task priority, then standard • Uses resource information such as: • Working time calendar • Maximum units • Assignment units • Microsoft Leveling does not level material or cost resources.
Level the Project • Review and cleanup resource utilization • Set exceptions (test plan) • Administration tasks • Recurring tasks • One per phase • Incorporate into task estimates
Managing the Plan • Enter time to your project • What happens when the project changes • Not IF the project changes • The paradigm shift • Seeing tasks in parallel vs. serial • Use the tool to help manage the project, instead of you managing the tool
Additional Topics • Managing and leveling across multiple projects • Using Microsoft leveling without entering actual time • EPM considerations
Questions ??? ??? ??? ??? ??? ??? ??? ??? ??? ??? ??? ??? ???