SDO Status. HMI & AIA & EVE all integrated onto SDO Doing “CPT” now. PER 15 March Deliver to KSC August Ready for launch 1 Dec THIS YEAR Likely launch still Jan ’09 JSOC development continuing Hardware ordered, some arrived, rest in March New hardware operating by April
E N D
SDO Status • HMI & AIA & EVE all integrated onto SDO • Doing “CPT” now. • PER 15 March • Deliver to KSC August • Ready for launch 1 Dec THIS YEAR • Likely launch still Jan ’09 • JSOC development continuing • Hardware ordered, some arrived, rest in March • New hardware operating by April • DRMS/SUMS nearing completion • Export tools lagging • Level-0 done soon (c. 2 weeks) • Level-1 getting started • Level-2 (pipeline modules) ready to get moving ASAP • Teams Meeting in March – register by 7 Feb. • Hope for “SDO Science Center” AO before March – NOT FINAL YET !!!