100 likes | 183 Views
Impacts of Mod 244. Steve Nunnington xoserve. Background. 96.5% of transportation charges based on capacity. These are dependent on historical throughput. Capacity charges on DM sites are based on:- Bottom Stop SOQ. (BSSOQ) applicable to certain Interruptible sites. DM SOQ.
E N D
Impacts of Mod 244 Steve Nunnington xoserve
Background • 96.5% of transportation charges based on capacity. • These are dependent on historical throughput. • Capacity charges on DM sites are based on:- • Bottom Stop SOQ. (BSSOQ) applicable to certain Interruptible sites. • DM SOQ. • Interruptible sites still pay 50% of firm costs. • BSSOQ can only be amended in the AQ Amendment window. • BSSOQ is based on the consumption of the Uncapped Winter Peak. (Highest daily demand between Oct – May) • Challenges are currently only allowed to those meter readings and consequently their derived consumption. • Number of challenges are very low.
Background • DM SOQ can only be reduced by shipper from October to January each year. • DM SOQ cannot fall beneath the value of the prevailing bottom stop SOQ. • DM SOQs are all passed to Networks for approval be they increases or decreases. • DM mandatory level is AQ of 58,600,000 Kwh below which they become voluntary. • Interruptible threshold AQ of 5,860,000 Kwh below which sites cannot be interruptible. • DM threshold. Site cannot be DM below AQ of 73,200 Kwh. There are currently 158 of these. • AQ needs to be reduced in line with SOQ to ensure the supply point falls within the correct charging band. • Ratchet mechanisms currently apply only Oct – May. • All these processes are fully systematised and are robust.
Analysis • There are 2058 DM supply points on xoserve systems. • Under Mod 244 there would be the following eligible sites:- • DM Interruptible 1410 • DM Firm Mandatory 185 • TOTAL 1595 • There are also 115 Unique Sites which qualify under the terms of the Mod but these could be dealt with under current US off line processes.
Analysis • This would mean under the terms of Mod 244 for all DM Mandatories the number of candidate sites would be as follows • 20% 587 • 30% 479 • 40% 400 • 50% 350 • Additionally 51 US would fall in line with the 20% rate. Looking ahead • Should BSSOQ as a concept be scrapped or the definition be changed? (E.G AQ/365) • Should we allow DM SOQ appeals throughout the year? • Should ratchets be applied all year round for eligible sites?
Possible solutions • Rebates on Billing (Off-Line) • Bills issued as normal using SOQs • Rebate issued at M+2 to amended SOQ values • Monitoring of usage against various thresholds and consumption • Ratchet process required • Admin charge • Re-confirmation of the site under a new MPRN. (Off-Line) • Co-ordinated end date of MPRN and creation of new one • New values to be applied to new MPRN • Monitoring of usage against various thresholds and consumption • Ratchet process required • Admin charge • System solution (On-Line) • Investigating availability of a screen to amend BSSOQ. • Window for reducing DM SOQ may be parameterised. • Develop solution to monitor and carry out correct solutions when breaches apply.
Risks of an Off Line Solution • UK Link may not reflect true values • Labour Intensive. • Unique Sites process handles 115 sites. • Very labour intensive • Deals with around 20-25% of throughput • With 4.75 FTEs • Mod 244 currently has 587 candidates • Daily monitoring • Reads • SPA process (Does the Mod span transfers?) • Thresholds • Ratchets • Admin charge
Risks 2 • Demand forecasting for Networks • Potential for manual errors in Billing • AQ could be out of sync with SOQ. • Process required to increase SOQ/AQ when site returns to normal production • Incorrect information regarding capacity availability. • Potential emergency impact if interruptible values are incorrect. • Development of off-line solution may be time consuming. Estimates range from 3 – 6 months from Ofgem approval. • Where shippers fail to comply there are complex activities such as ratchets that will need to be undertaken which will be both time consuming and labour intensive. • If analysis is incorrect and large volumes of supply points are submitted through this process the developed solution may not be appropriate. • DM CSEPS have not been considered along with impacts on IGTs.
Conclusions • Mod 244 should be driven by take up. • Small numbers will mean off line system • Larger numbers mean that a systematised solution is essential.