An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The CERN Target Experiment Schedule and Budget MERIT Review BNL December 12, 2005

  2. The Funding Profile

  3. High Field Pulsed Solenoid • 80o K Operation • 15 T with 5.5 MW Pulsed Power • 15 cm warm bore • 1 m long beam pipe Peter Titus, MIT

  4. Pulsed Solenoid Milestones • Delivery to MIT December 05 • Reception Testing January 06 • Integration Testing September 06 • Ship to CERN November 06 • Installation at CERN December 06

  5. The Hg Jet System Double Containment System, with snout inserted into magnet. Mercury inventory ~ 20 liters. Hydraulic system can deliver up to 1000 psi, to propel mercury at > 20 m/s

  6. Hg Jet System Milestones • Delivery of Hydraulics February 06 • Containment Vessels May 06 • Optics Delivery June 06 • System integration at ORNL June-July 06 • Integration Testing at MIT September 06 • Ship to CERN November 06 • Installation at CERN December 06

  7. Target Test Site at CERN

  8. The Tunnel Complex TT10 Hyd Pump & Controls in TT2 ISR (Control Room Location) MERIT TT2A TT2

  9. Surface above the ISR Two 18kV sub-stations 6000 l Dewar Access Route One 18kV Sub-station

  10. Power Converter (From SPPS Transfer Line) 8000 Adc, 1000 Vdc • Strategy: • Refurbishment of the West Area Power Converter, making it compatible with the project requirements Passive filter Rectifier bridges Global view Passive filter capacitors self capacitors DC output

  11. Power Supply Milestones • Site Preparations January 06 • Relocate and Install February 06 • DC Cabling February 06 • AC Cabling March 06 • Refurbish PS March-April 06 • Interlocks September 06 • Commissioning October 06

  12. Cryosytem Layout LN2 and N2 gas stored on the surface. Cold valve box in the TT2 tunnel. Exhaust gas vented into TT10 tunnel through filtration system. ~ 150 liters of LN2 per Magnet pulse. Magnet flushed with N2 prior to each pulse, to minimize activation of N2.

  13. Cryogenics Process and Instrumentation

  14. Cryogenic System Milestones • TT10 Vent Installation January 06 • Cold Valve Box Fabrication April-July 06 • Control System Development January-June 06 • Surface Preparations May 06 • Transfer Line Installation July 06 • Cold Valve Box Testing October 06 • Heater System Installation September 06 • Cold Valve Box Installation November 06 • Commissioning December 06

  15. Project Major Sub-systems

  16. CERN Infrastructure