BE-BI activities in LS2

This project involves general maintenance, new equipment installation, and supporting other renovation activities to enhance BI facilities. Activities include LINAC4 connection, BLM installation, and ECR finalization. Current activities ensuring BI equipment readiness while aligning with accelerator schedules. Key equipment installations in various locations within the PS complex.

Download Presentation

BE-BI activities in LS2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BE-BI activities in LS2 PS complex LS2 BI activities

  2. General maintenance • LIU • LINAC4 connection • Consolidation • New BLM installation • Support to other activities(i.e. MU renovation, BI/BT line refurbishment,…) PS complex LS2 BI activities

  3. No major problems detected so far • BI equipment readiness complying with accelerators schedules • Other activities may influence some of the BI activities • Few BI equipment might be ready just in time • BLM activities were missing but now in the planning • Some ECR still to be finalised PS complex LS2 BI activities

  4. New SEMGRID in SS48 and 54 LIU WS in SS 64, 65, 68 and 85 New SEMGRID in SS42 • BTP refurbishment: • Relocate beam instrumentation • New BLM • New BPM New BGI V in SS84 BCT removal in SS26 New BLM installation LINAC4 connection PS complex LS2 BI activities

  5. BTP line: • Relocate beam instrumentation • New BLM • New BPM LIU WS(4x) in 11L1 LIU WS(4x) in 4L1 New SEMGRID New BLM installation • BI-BT line renovation: • Relocate beam instrumentation • New BLM • New BPM PS complex LS2 BI activities

  6. Completion and connection of LINAC4: LINAC2 dismantling New BLM installation PS complex LS2 BI activities

  7. Questions? Thanks PS complex LS2 BI activities