1 / 14

ENVISAT Calibration Review

ENVISAT Calibration Review – ESTEC – 9/13 Sept 2002. SCIAMACHY Operations Support by Manfred Gottwald - DLR-IMF. ENVISAT Calibration Review. - DLR/IFE. SCIAMACHY Operations Support in Commissioning Phase - SODAP integrated in overall SCIAMACHY team

jackie
Download Presentation

ENVISAT Calibration Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ENVISAT Calibration Review – ESTEC – 9/13 Sept 2002 SCIAMACHY Operations Support by Manfred Gottwald - DLR-IMF ENVISAT Calibration Review - DLR/IFE

  2. SCIAMACHY Operations Support in Commissioning Phase - SODAP • integrated in overall SCIAMACHY team • 'front-end' of SCIAMACHY measurement related activities (e.g. maintenance & operations of GS interfaces to FOCC and RGT) • close liaison with overall planning and engineering related activities at Astrium • main SOST responsibilities - command & control: CTI tables & timelines - mission planning: SCIAMACHY measurement plans - instrument monitoring: long-term behaviour (see also separate presentation by SOST-IFE)

  3. SCIAMACHY Operations Support in Commissioning Phase - Validation • responsibility for measurement programme definition & implementation (in close cooperation with partners) • quasi-nominal operation of GS interfaces to FOCC and RGT • close liaison with engineering related activities at Astrium if required (e.g. decontamination) • close interface with validation scientists - support to optimum planning of validation campaigns (e.g. aircraft, balloon) - nadir/limb overflight predictions • preparation of Final Flight operations

  4. Command & Control in SODAP (1) • CTI table = parameter file to define the parameter settings for specific measurement characteristics of the instrument • CTI tables configured the instrument for the specific SODAP and validation needs • timescale (CTI table generation to submission) - approx. 1 week for pre-planned activities - < few days for ad-hoc activities (re-planning due to non-nominal events)  close cooperation with MP at FOCC • first delivery of CTI tables occured for orbit 239, since then exchange of about 7900 CTI tables in total (about 30 SODAP configurations implemented)

  5. Command & Control in SODAP (2) • secure ftp i/f between SOST and FOCC was very stable • all CTI table exchanges were successfull no pre-planned SCIAMACHY operations lost due to CTI table i/f problems • SODAP was most demanding phase for command & control i/f between SOST to FOCC • command & control i/f between SCIAMACHY and ENVISAT ready for nominal operations • command & control i/f during validation is quasi-nominal: CTI table exchanges only for interleaved SODAP measurements and implementation of Final Flight settings

  6. Mission Planning in SODAP (1) • all MP activities had to be compliant with ENVISAT System SODAP and to be harmonized with SCIAMACHY engineering activities (SCOOP) • each change in main SODAP status configuration required to use a specific set of timelines • each change in main SODAP status configuration triggered the generation of a new Orbit Sequence Definition File (OSDF) • timescale (generation to submission) - approx. 1 week for pre-planned activities (OSDF and timelines) - < few days for ad-hoc activities (OSDF re-planning due to non-nominal events)  close cooperation with MP at FOCC

  7. Mission Planning in SODAP (2) • top-down approach: • objectives •  • objectives implementation: • states, timelines, SCOMP •  • measurement implementation: • CTI parameter tables, CTI timelines, OSDF •  • i/F operations: • OSDF to RGT, states & timelines to FOCC

  8. Mission Planning in SODAP (3) • first delivery of timelines and OSDF occurred for orbit 238, since then exchange of about 400 timelines and about 30 OSDF in total • secure ftp i/f between SOST and FOCC (timelines) was very stable • secure ftp i/f between SOST and RGT (OSDF) was very stable • no pre-planned SCIAMACHY operations lost due to timeline or OSDF i/f problems • SODAP was most demanding phase for MP i/f between SOST and FOCC/RGT • MP i/f between SCIAMACHY and ENVISAT ready for nominal operations

  9. Mission Planning in Validation Phase • quasi-nominal operation of MP i/f • quasi-nominal SCIAMACHY measurement plans: scientific and calibration & monitoring rules • implementation of specific validation requirements whenever possible and known in advance (MP i/f timescales) • MP support to planning of external measurement campaigns (e.g. aircraft) on request • specific validation related information provided to user community via SOST website

  10. Instrument Monitoring (1) • split of tasks between SOST-IFE and SOST-DLR • SOST-DLR: - selected HK telemetry - level 0 data • SOST-IFE (separate presentation): - level 0 data - level 1b data • first measurements for long-term instrument monitoring during validation phase (quasi-nominal operations) • problem (HK/L0): developed tools are based on complete, consolidated orbits - current data/telemetry delivery not always compliant

  11. Summary • SODAP was most demanding phase of the SCIAMACHY mission w.r.t. - command & control - mission planning • command & control i/f SCIAMACHY - ENVISAT  • mission planning i/f SCIAMACHY - ENVISAT  • telemetry (FOS) and data (PDS) access require improvement

  12. What Next? • optimization of Final Flight operations concept, comprising - scientific measurements - calibration & monitoring measurements - states (D to consolidated b-states) - timelines (D to timelines executing consolidated b-states) Note: current status of validation measurements indicates only small modifications between Final Flight and consolidated b-states • i/f to background engineering monitoring at FOCC - APSM Health Check - PMD/SF ADC calibration - OA temperature monitoring - RRU monitoring - LLI monitoring

  13. Specific SCIAMACHY Mission Planning Tools • ROE Parser to extract SCIAMACHY relevant information from ROE • Timeline Scheduler to generate simulated DMOP (only SCIAMACHY entries)  check OSDF before submission to RGT • DMOP tool to - extract SCIAMACHY relevant entries from DMOP and generate userfriendly 'SCIAMACHY DMOP = SDMOP' - generate geolocation information for nadir and limb • Mission Planner to generate OSDF: to be ready when Final Flight operations concept is implemented (scientific and calibration & monitoring rules) • MP information provided to user community via SOST website under http://atmos.af.op.dlr.de/projects/scops/

  14. Instrument Monitoring (2) • example: HK telemetry

More Related