JWST PRDS Project Mangement Case Study

JWST PRDS Project Mangement Case Study. Jesse Doggett Project Engineer, ITEB/OED. What is the JWST PRDS? Stakeholders & Communication PRDS Formal Documents Planning and Subprojects Managing Change Quality. Outline. Project Reference Database Data Used to Operate the Space Craft

jadzia
Download Presentation

JWST PRDS Project Mangement Case Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. JWST PRDS Project Mangement Case Study Jesse Doggett Project Engineer, ITEB/OED

  2. What is the JWST PRDS? Stakeholders & Communication PRDS Formal Documents Planning and Subprojects Managing Change Quality Outline JWST PRDS Case Study

  3. Project Reference Database Data Used to Operate the Space Craft PRDS Functional Components Data Editor Version Control Dependency Checking Change Management JWST PRDS JWST PRDS Case Study

  4. JWST WBS (Work Breakdown Structure) JWST PRDS Case Study

  5. Stakeholders NASA, NGST, Instrument Teams, ISIM, WFS&C, OSS, S&OC, PRDS Team Communication Working Group Meetings Status, Requirements, Interfaces, Design Formal Documents NGIN - JWST Restricted Web Site Stakeholders / Communication JWST PRDS Case Study

  6. Planning Documents Architecture, Operations Concept, Requirements, Design Acceptance Documents Test Plan Test Results Release Notes Other Interface Control Document Formal Documents JWST PRDS Case Study

  7. Basic Plan Project broken up into phases or sub-projects. Initial phase, implement baseline set of requirements. Subsequent phases, requirements and bug fix implementations tracked in the Problem Report System Delivery Procedures Minor Releases (bug fixes) E-Mail Notification, Delivered via Download Major Releases (new requirements) Formal Documents, Government Witness for Acceptance, Contracting Officer Delivers CD and Hard Documents Planning and Subprojects JWST PRDS Case Study

  8. Requirements Informally Discussed in Working Group Meeting Formal Request to Change Is Negotiated New Requirements Document Approved and Updated Important to Agree with Government on the Set of Requirements Personnel Unplanned Departures Between First 2 Phases Worked with Division to Identify Other Available Personnel Slipped Schedule a Few Weeks Managing Change JWST PRDS Case Study

  9. ~20 New Requirements / No New Funding Initially, Informed NASA We Can’t Set Completion Date “Rolling Wave Planning” Create and Refine Schedule and Plan Design-As-We Go Acceptance Test Only at the End Certification Requirements JWST PRDS Case Study

  10. Quality Assurance Ensures that activities are being performed to verify requirements are met. Not formally done for PRDS Quality Control Software Testing for PRDS Perform Regression and Problem Report Testing Weekly Reports Results Driver Future Action Document Failures Determine If Immediate Fixes Required to Release Quality Planning JWST PRDS Case Study