390 likes | 531 Views
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting for SunGuide Release 4.0 August 18, 2008. Introductions. Agenda. Logistics. Test location: ITS Demo Lab Breaks: Rolling Lunch SwRI Cafeteria Internet: Available in the lobby (100baseT connection). Restrooms.
E N D
SunGuideTM Software Development ProjectTest Readiness Review (TRR) Meeting for SunGuide Release 4.0August 18, 2008
Introductions SunGuide 4.0 TRR
Agenda SunGuide 4.0 TRR
Logistics • Test location: • ITS Demo Lab • Breaks: • Rolling • Lunch • SwRI Cafeteria • Internet: • Available in the lobby (100baseT connection) Restrooms Restrooms Demo Lab Lobby Restrooms SunGuide 4.0 TRR
Current Project Status • Release 4.0 Development Complete • 115 Requirements • SwRI has been running: • Data stream to the FL-ATIS team for over 12 weeks • In the lab for 3 weeks • SwRI has exercised the system • Unit testing • Ad hoc testing • Dry runs of the SICP SunGuide 4.0 TRR
Architecture: What Changed? 511 Removed SunGuide 4.0 TRR
Test Hardware Layout SunGuide 4.0 TRR
Discuss Lab Configuration SunGuide 4.0 TRR
Discuss Lab Configuration :SwRI Server Farm • SAN: • Two drive bays • 6 fiber connected hosts • FAT: • Two DL380s: • Laplace • Pythagoras • Development: • Six DL380s • Eight DL370s SunGuide 4.0 TRR
Environment Note • Note that SwRI has both “real” equipment and simulators in the lab • There are times that the simulators “mis-behave” and we find ourselves “re-testing” to achieve the results • The “re-tests” do NOT require software modifications • For example, one time a drunk driver took out the power (actually causing a short on the power lines and toasted a number of devices such as voice mail) to SwRI and the Cortec Codecs have never been the same. • SwRI has other project’s that will occasionally (accidentally) “hit” our development devices SunGuide 4.0 TRR
Discuss Testing Process • Purpose: • Review preparations for testing • Walk through the test procedures at a very high level and determine if anyone has any comments • Ground Rules: • Testing will not depart from the written procedures • Any requested “ad hoc” testing will occur after the formal testing process • Re-writing of requirements / scope additions will be captured for future consideration • Approvals: • FDOT/SwRI will witness each test case (on “Master SICP”) • At the conclusion, FDOT will sign SICP cover page to acknowledge all tests were executed as written/noted in the “Master SICP” SunGuide 4.0 TRR
How Testing Will Occur • For each Integration Case (IC): • SwRI will explain the objective of the IC • Requirements will be reviewed • A “reader” will walk through each test case (see next slide for an ‘example’ test case) • An “operator” will perform the GUI actions • Results will be captured • Note: Enhancements will be captured for future review by FDOT SunGuide 4.0 TRR
Test Case Example SunGuide 4.0 TRR
Review Test Procedures • IC-1: Admin Editor (AE) • IC-2: Configuration (CFG) • IC-3: Events (EV) • IC-4: SAE Codes (SAE) • IC-5: Alternate Roads (ALT) • IC-6: Video (VID) • IC-7: Floodgates (FG) • IC-8: Center-to-Center (C2C) • IC-9: Reporting (REP) • IC-10: Database (DBASE) • IC-11: Miscellaneous (MISC) SunGuide 4.0 TRR
General Discussion Questions About Test Cases? SunGuide 4.0 TRR
Open Discussion SunGuide 4.0 TRR
Agenda SunGuide 4.0 TRR
Florida Statewide 511 System ConceptFrom FDOT Data Fusion Requirements Document SunGuide 4.0 TRR
FLATIS Functional SubsystemsFrom FDOT Data Fusion Requirements Document • DFS provides data to IDS via C2C • SunGuide data and other local and district sources SunGuide 4.0 TRR
Release 4.0 and FL-ATIS Responsibilities • SunGuide C2C is the “transport mechanism” • If other agencies (e.g. OOCEA) wish to provide data it MUST comply with the SunGuide C2C interface requirements SunGuide 4.0 TRR
C2C Infrastructure Concept:Deploying a C2C “Cloud” SunGuide 4.0 TRR
How SunGuide Data gets to FL-ATIS… • Data: • In general, as SunGuide updates data it is immediately transmitted to the C2C • C2C pushes data to a receiver’s plugin, from there, the processing of the data is the burden of the receiver • Data Format: • Specified in the SunGuide Center-to-Center Interface Control Document (ICD), last published on July 25, 2008 SunGuide 4.0 TRR
R4.0 Conceptual Data Flow SunGuide 4.0 TRR
Providing Data to Other “Consumers” (3rd Parties) • C2C: • Is the “method” SunGuide uses to transmit data outside the “domain” of a SunGuide deployment. • Was built using the available ITS Standards produced by NEMA, AASHTO, and ITE. • The 3rd party feed identified in FDOT DFS document will be a “C2C feed”. • C2C ICD: • Has been published (this describes how to access the data). • To access the data feed a program has to be developed that access the web service that provides data in XML format (see the C2C ICD). • Suggestion to develop an application that simply deposits the data every ‘x’ minutes onto a FTP server has been made. • Note: the www.fl511.com developed for Release 3.0 used C2C as the source for data. SunGuide 4.0 TRR
SunGuide Event Processing SunGuide 4.0 TRR
Weather Processing SunGuide 4.0 TRR
External Events Note: “nearby” distance is configurable SunGuide 4.0 TRR
Restricting Publishing of Events • Operator can determine if an event is published to FL-ATIS: SunGuide 4.0 TRR
Floodgate Processing • FDOT provided an Excel spreadsheet with all possible Floodgate combinations • Converted to XML file by FDOT • SunGuide uses XML file which allows a “soft” configuration – any changes to the file need to be SIMULTANEOUSLY coordinated across SG deployments and FL-ATIS SunGuide 4.0 TRR
Floodgate - continued • Each floodgate: two audio recordings, two text entries • Each banner: two text entries SunGuide 4.0 TRR
Floodgate - continued • Status: • Retrieved from the FL-ATIS C2C plugin database (THIS IS THE SOURCE FOR FLOODGATE STATUS) • Sent to C2C for distribution • Transmitted to each deployment “subscribed” for Floodgate status data • Selecting banner/message takes operator back to “entry” screen so edits can easily performed SunGuide 4.0 TRR
DMS Processing SunGuide 4.0 TRR
CCTV Processing SunGuide 4.0 TRR
Travel Time / Traffic Conditions • TSS generated “link” data published as available (e.g. a lot of detectors implies a lot of C2C data) • TvT (Travel Time) data published at the rate of a “tunable” TvT parameter (e.g. C2C publishes as it arrives) SunGuide 4.0 TRR
SAE Code Interpretation • SAE Description is updated whenever Event is “Saved”. SunGuide 4.0 TRR
Event Management:Configuration Screens – 4.0 Changes • View the Configuration of (note these are view only as of Release 4.0 due to FLATIS): • Event type SunGuide 4.0 TRR
Event Management:Configuration Screens – 4.0 Changes • View the Configuration of (note these are view only as of Release 4.0 due to FLATIS): • Vehicle tracking: vehicle types SunGuide 4.0 TRR
Test Data Sources • Two sources of data: • SwRI Test Data feed (FULL feed available since May 16) • XML Tester (a ‘controlled’ tool) SunGuide 4.0 TRR
Agenda SunGuide 4.0 TRR