Queries raised by Director (Tariff) on ARR and Tariff Application of CESU for FY 2011-12 on 05.02.2011.
E N D
Queries raised by Director (Tariff) on ARR and Tariff Application ofCESU for FY 2011-12 on05.02.2011
Some DISCOMs have proposed to levy Monthly Minimum Fixed Charge (MMFC) in respect of LT Industry(S), LT Industry(M), SPP(LT) and PWW(LT) in terms of KVA. In this connection, CESU may submit whether the above category of consumers are having meters with facility of reading in KVA. • Some DISCOms have opted for KVAh billing in place of existing KWh billing. CESU may submit an estimation of consumption data with KVAh billing as well as with KWh billing and the difference thereof and also the revenue implications. • CESU should submit status of Bachata Lamp Yojana (BLY) of BEE as directed by the Commission in the last tariff order with their programme of implementation.
Some DISCOMs have proposed to levy demand charges on emergency drawal by CGPs of their region apprehending misuse of Clause 80(15) of the Distribution Code. In this context, CESU may submit month-wise individual emergency drawal of CGPs within its area of supply along with their respective rated capacity of the largest unit. • CESU has submitted audited accounts for FY 2008-09. The licensee is required to submit the audited accounts for FY 2009-10. They should also explain as to why they are lagging in submission of updated audited accounts. • CESU should submit month-wise cash flow statement for the FY 2010-11 (actuals upto end of January, 2011) considering the revenue items only. • OERC had asked DISCOMs vide letter No.238 dtd.28.01.2011 to submit the DSM activities to be undertaken by them during 2011-12 alongwith their respective costs and benefits. Nothing has been received from CESU so far. CESU may submit the relevant details for FY 2011-12 to the Commission.