FUI Stakeholder Group 3rd December 2008 Congestion Management project

FUI Stakeholder Group 3rd December 2008 Congestion Management project. Recap. National Grid and RTE are progressing the Capacity Management System project to achieve CM Guidelines compliance. Slides presented on 4 July 08 are available at:

jamese
Download Presentation

FUI Stakeholder Group 3rd December 2008 Congestion Management project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FUI Stakeholder Group3rd December 2008Congestion Management project

  2. Recap • National Grid and RTE are progressing the Capacity Management System project to achieve CM Guidelines compliance. • Slides presented on 4 July 08 are available at: • www.nationalgrid.com/uk/Interconnectors/France/GeneralInfor/

  3. Progress • Since 4 July SG we have: 31/7 - contract awarded for CMS supplier 7/8 - tender launched for Hosting / Managed service 3/10 - conducted User & Regulator consultation on commercial aspects 14/10 - consultation results shared with Regulators 30/10 - provided IFA Users with a summary of certain Access Rules principles 30/11 - software design stage completed

  4. CMS Project scope • CMS will handle all IFA commercial aspects, including auctions, credit management, nominations across all timescales LT, D-1, Intraday. • In addition, CMS project requires National Grid / RTE to modify various internal processes, eg: • IS interfaces: • Control Room IS interfaces • Market operator interfaces (eg Elexon, RTE) • Back office systems • ETSO Vista • Documentation: • IFA Access Rules • Operational procedures • SLAs • Processes • Control room functions • Back office process (credit management / invoicing).

  5. Next Steps in 2009 Jan - award contract for Hosting & Managed service Jan-Feb - consult IFA Users on draft Access Rules Feb - Factory Acceptance Tests (FAT) Apr-May - Site / User Acceptance Tests (SAT / UAT) May - publish IFA Access Rules June - Availability Testing & User Training July - Go Live