Congestion Management Work Group Update For WMS 3-18-09 Marguerite Wagner, PSEG Texas
Topics Discussed • Business Process for Adjusting TTC for TCR auctions • Singleton Outage • San Angelo – Menard • NOGRR 25
TCR Determination: # of TCRs for Auction • Protocols 7.5.3.1 provide ERCOT with authority to adjust # of TCRs for sale • “…in determining the amount of TCRs available in each monthly auction, ERCOT shall seek to achieve revenue neutrality and avoid a revenue shortfall due to payment to TCR holders for the month.” • ERCOT Proposal: Congestion Costs + TCR Revenues – TCR Payment = 0 • CMWG Discussion – Auction Revenues should not be considered in the revenue neutrality evaluation • One alternate proposal discussed at CMWG: Congestion costs + TCR revenues for oversold #TCRs only - TCR payments = 0
TCR Determination: Questions for WMS • Should ERCOT adjust number of TCRs for sale in monthly? • Affects ability to hedge ‘prompt month’ • Historical Congestion Rents Not Sufficient to Cover Pay Out • Due to difficulty to forecast avail Transmission Capability in RT • Should improve with longer lead times for Outage Submission
Singleton Substation Construction • ERCOT presented outline outages being taken to allow construction of Singleton Sub • 3/20 – 4/9: various coincidental outages of Tomball-Jewett configurations • Since then ERCOT determination to implement “conditional” NH CREs • Peters to Flewellen 138kV line and the Tomball to Hockley 138kV line as CREs Houston
San Angelo - Menard • Issue identified by IMM • ERCOT discussed potential CRE—but line currently outaged—delaying request • Significant OOMing for control • Potential 2010 CSC? • Stay tuned San Angelo
Upcoming Work Items for CMWG • CREs • Do we need refinement in protocols about PTDF effectiveness before 2010 CSC determination? • Last year were guided by 3%/5% • Balance ERCOT/Market use/understanding of “conditional” CREs • Nodal • CCT • NOGRR 25
NOGRR 25 – OWG Request to CMWG Develop Metrics for Nodal Protocols • 9.12.4(a)8.2(2)(d)Three consecutive days of a particular congestion constraint (constraints passed to Security-Constrained Economic Dispatch (SCED) from Network Security Analysis (NSA)) in Real-Time not identified in the Day Ahead Market (DAM); • 9.12.4(b)8.2(2)(d)Two consecutive hours of a particular congestion constraint in Real-Time not identified in the Hourly Reliability Unit Commitment (HRUC) process; • 9.12.4(c)8.2(2)(d)Two consecutive days of a particular congestion constraint in Real-Time not identified in the Day-Ahead Reliability Unit Commitment (DRUC) process.