Consultant Selection. ACEC-Illinois/ IDOT-Region 1 Local Roads Seminar March 7, 2013. Kevin Burke III, P.E. Local Policy & Technology Engineer kevin.burkeiii@illinois.gov 217.785.5048. Outline. When QBS Is Required QBS Process Types of Consultant Contracts Length of Services
E N D
Consultant Selection ACEC-Illinois/ IDOT-Region 1 Local Roads Seminar March 7, 2013
Kevin Burke III, P.E. Local Policy & Technology Engineer kevin.burkeiii@illinois.gov 217.785.5048
Outline • When QBS Is Required • QBS Process • Types of Consultant Contracts • Length of Services • Conflict of Interests
When QBS IS Required • Federal Funds • Total contract exceeds $150,000 • Contract value determine by phase • Unless, same consultant performing multiple phases • State Funds • Not an emergency • Total contract exceeds $25,000 • No existing relationship* • Local Public Agency (LPA) not home rule unit
QBS Process • Define Project • Public Notice • Evaluation • Selection • Contract Negotiation
Define the Project • Need, Purpose, and Objective • Various Components • Timetable • Unique Situations or Known Problems • Budget • DO NOT REQUEST COST INFORMATION • Required for Existing Relationship
Types of Engineering Contracts/ Length of Service • Project Specific • Multiphase • Master Task Order • Maximum Length 10 Years
Public Notice • Mail Notice or Publish in Newspaper • Request Statement of Interest • DO NOT REQUEST COST INFORMATION • Electronic Notifications?
Evaluation • Evaluate All Proposals • Eliminate Non-Qualified Respondents • May Consider Requiring Presentations • Minimum of three (or all qualified) • DO NOT CONSIDER COST
Selection • Minimum of Three • Contact Highest Ranking for Negotiation • Repeat if Necessary
Negotiation • Fair and Reasonable Compensation • Ensure Scope Is Understood • Refine and/or Amend Scope • Establish • Project Schedule • Manpower Requirement • Responsibility • Execute Agreement
Compensation Formulas • Lump Sum (FA, State, MFT) • Specific Rate (FA, State, MFT) • Cost Plus Fixed Fee (FA, State, MFT) • Direct Labor Multiplier (State, MFT) • Actual Cost (State, MFT) • Base Fee (MFT Maintenance)
Conflict of Interests • Actual or Appearance • LPA Official with Interest • Interest in Acquired Property • Design and Construction Consultant
Phase III Issues • In Responsible Charge • Resident Qualifications • Inspector Qualifications