ASTRON. EMBRACE Project status G.W. Kant. EMBRACE concept. ‘analogue’ tiles RF transport to central processing facility 50.000 antenna elements. Tile Baseline architecture. EMBRACE. Embrace is a development/production project, given the size and the time frame
E N D
ASTRON EMBRACE Project status G.W. Kant
EMBRACE concept • ‘analogue’ tiles • RF transport to central processing facility • 50.000 antenna elements
EMBRACE • Embrace is a development/production project, given the size and the time frame • Use currently available technology • If possible enhance EMBRACE with DSX outputs
EMBRACE DS5 Tasks Original estimates • DS5 – Coordination (48mm/4fte) • DS5 – T1 Design and development of (382mm/32fte) • DS5 – T2 Production of EMBRACE (244mm/20fte) • DS5 – T3 Test the EMBRACE systems (190mm/16fte)
EMBRACE DS5 Deliverables • Discuss/define DS5 – T3 deliverables first at SKADS level • T3 deliverables are now detailed to a sufficient level to proceed • T3 deliverables have to be enhanced further (parallel to T1/T2 activities)