Tools for coordination:Powering Tests Visualization Tools Álvaro Marqueta Review of the commissioning of sector 45 February 28, 2008
Why…? LSA Test plan, PC operational parameters, … Test results & comments, analysis key for PM … Defining new Sets Of Circuits, Block/unblock circuits, … Info used to sign off tests with PM tool … Post Mortem SOC Editor Sequencer MTF
Summary • The problem… • Great amount of data stored in LSA. Should be accessible somehow. • There is a need of an online access to the info of the tests being executed at CCC. • Fast & easy access via a web interface. • The solution?? • Tool to follow the evolution of the Powering Tests: what’s going on. • Access to the history of tests, given date, circuit… • Display operational parameters from Power Converters. • … 3
Where…? Powering tests From HCC main page -> The Field… 4
Overview Choose main view Define search patterns Choose which data show/hide Tests under execution Tests executed today Tests executed yesterday Tests w. pending PM analysis Operational SOCS Blocked circuits 5
Main screen Last executed: Ok Test pending expert analysis with post mortem tools Last executed: Not Ok Test to be repeated Last executed: Ok Test passed Status/progress of the powering tests given a group of circuits 6
Tests under execution • Follow up of tests under execution: • As soon as the sequencer launches a test • it is visible on the screen. Test currently under execution 7
Report of day / circuit • Given a calendar day or a circuit name • Shows status of each test passed • Ok, not ok, waiting PM • Comments from operator/sequencer 8
Other features… Global overview of test progress Operational parameters from Power Converters 9
Dashboard: the sector • Displays whole sector in one screen. • Allows following commissioning of other activities prior to powering. • Circuits groped by class / functionality • Cryo start and cryo maintain visible. • Linked to the powering test tool. 10
Possible extension for planning Last executed: Ok / Not Ok Test already executed Tests planned for execution During next day/week 11
Other possible add-ons • Possible ways to add extra functionality: • Merge all PIC2 tests to save screen space • Customize list of circuits: given a SOC • Direct link circuits/tests in MTF • Display MTF properties • Ultimate current reached per circuit • Non conformities attached to circuits • Possible extension to help planning visualization 12