1 / 31

Construction Cost Impacts Florida DOT Experience

Construction Cost Impacts Florida DOT Experience. 20 th Annual TEA Conference – 2007 St. Louis, Missouri October 5, 2007. Greg Davis State Estimates Engineer Florida Department of Transportation. OVERVIEW. Material Prices Work Program (STIP) Bidder Competition Lake Belt Mining Issue

jatin
Download Presentation

Construction Cost Impacts Florida DOT Experience

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Construction Cost ImpactsFlorida DOT Experience 20th Annual TEA Conference – 2007 St. Louis, Missouri October 5, 2007 Greg Davis State Estimates Engineer Florida Department of Transportation

  2. OVERVIEW • Material Prices • Work Program (STIP) • Bidder Competition • Lake Belt Mining Issue • FDOT Strategies

  3. MATERIAL PRICES

  4. Earthwork Average per Cubic Yard Fiscal Year – Statewide (thru August 2007) NOTE: Lump Sum, Design/Build Contracts not included in this graph

  5. Asphalt (Structural/Friction Course Items only) Average per Ton Fiscal Year – Statewide (thru August 2007) NOTE: Lump Sum, Design/Build Contracts not included in this graph

  6. Structural Concrete Average per Cubic Yard Fiscal Year – Statewide (thru August 2007) NOTE: Lump Sum, Design/Build Contracts not included in this graph

  7. Structural Steel Average per pound Fiscal Year – Statewide (thru August 2007) NOTE: Lump Sum, Design/Build Contracts not included in this graph

  8. Reinforcing Steel Average per pound Fiscal Year – Statewide (thru August 2007) NOTE: Lump Sum, Design/Build Contracts not included in this graph

  9. SummaryStatewide Weighted Average Prices (Fiscal Year)

  10. WORK PROGRAM (STIP)

  11. (Projects rejected and deferred to 05/06 have been removed)

  12. IMPACTS TO FLORIDA’S PROGRAM • First impact occurred in FY05/06 • Rejected 71 contracts because of high bids • These were advertised at $600M and bids came in at $977M • 28 of these were re-let. • 43 contracts were rolled into FY 06/07 or deleted.

  13. IMPACTS TO FLORIDA’S PROGRAM • FY06/07 Impact • Rejected 11 contracts because of high bids • These were advertised at $23.1M and bids came in at $37.3M • 2 of these were re-let. • 9 projects were deferred to 07/08 or deleted. • FY07/08 – 1 rejected contracts todate

  14. BID COMPETITION

  15. LAKE BELT MINING ISSUE

  16. LAKE BELT MINING ISSUE • Large mining area in South Florida • Home to four of Florida’s largest mines • Supplies 1/4 of State’s Limestone • Supplies 1/2 of Aggregate for Asphalt • Ruling in late July 2007 • Immediately stopped 1/3 of all mining • Ruling is being appealed

  17. LAKE BELT MINING ISSUE • Ruling Affect on Material Cost • Concrete suppliers are not immediately affected • Limerock up $5/ton - Aug 1st • Asphalt Aggregate up $5-$10/ton – Aug 1st • Initially, cost increases are expected in southern half of the state only. • Statewide impact expected in Jan 2008

  18. FDOT STRATEGIES

  19. FDOT STRATEGIES • Alternative Contracting Methods • Bid Alternates • Bid Options • Scope Alternates

  20. FDOT STRATEGIES • Bid Maximum Specification Bid Maximum Report • Producer Price Index

  21. FDOT STRATEGIES • Not require everything to Federal-aid Standards • Only 25% of Florida’s Construction Program is funded by federal-aid dollars • Flexible Design and Engineering • We need to “Design what can be built easily” rather than “Build what can be designed easily”

  22. FDOT STRATEGIES • Increase Competition • Even during this volatility, contracts with 3 or more bids came in closer to our estimate • Waive bonds on smaller contracts to develop next generation of Primes • Simplify contract administration (inspection and testing) on smaller contracts • “Remove restrictions that do not add value” initiative. • Procure and permit sites for temporary asphalt plants for contractors to use

  23. CONTACT INFORMATION Greg Davis, P.E. State Estimates Engineer greg.davis@dot.state.fl.us (850) 414-4170

  24. Thank You and Any Questions!

  25. How ‘bout them Gators!

More Related