Cost Escalation MitigationFlorida DOT Approach Greg Davis State Estimates Engineer October 20, 2006
Reasons for Cost Escalation • Material Prices • Bidder Competition • Saturated Construction Market • Labor Shortages • Hurricanes
Earthwork - Statewide $4.96 $4.38 -11.7% $7.27 +66.0% $8.64 +18.8% NOTE: Lump Sum, Design/Build Contracts not included in this graph
Earthwork • Borrow Pit Availability • Hauling Cost • Real Estate Pressures
Asphalt – Statewide $53.93 $61.63 +14.3% $77.57 +25.9% $99.54 +28.3% NOTE: Lump Sum, Design/Build Contracts not included in this graph
Asphalt • Oil prices • Bitumen Prices • Aggregates
Structural Concrete – Statewide $760.89 +34.9% $564.12 +2.6% $549.82 $868.90 +14.2% NOTE: Lump Sum, Design/Build Contracts not included in this graph
Structural Concrete • Global Demand • Aggregates
Structural Steel – Statewide $1.06 $1.57 +6.1% $1.48 +39.6% $1.72 +9.5% NOTE: Lump Sum, Design/Build Contracts not included in this graph
Structural Steel • Global Demand for Steel • Fabrication Backlog • Transportation Cost
Reinforcing Steel - Statewide $0.91 +21.3% $0.96 +5.5% $0.75 +44.2% $0.52 NOTE: Lump Sum, Design/Build Contracts not included in this graph
Reinforcing Steel • Global Demand for Steel • Production Backlog • Transportation Costs
FDOT STRATEGIES • Deferred Projects • $1.0 Billion in projects (over 3-years) • Refine Awards Criteria • Normal Criteria • Additional Criteria • Rejected Contracts
FDOT STRATEGIES • Revised Inflation Rates YearCurrentPast • 1 7.0% 4.5% • 2 4.5% 4.0% • 3 4.0% 3.5% • 4 3.5% 3.3% • 5 3.5% 3.3%
FDOT STRATEGIES • Alternative Contracting Methods • Bid Alternates • Bid Options • Bid Maximum Specification
FDOT STRATEGIES • Comprehensive Price Index • DOT Borrow Pits • Temporary/Portable Asphalt Plants