A2 Motorway Project: Overcoming Challenges for EURO 2012

Learn about the successful completion of the A2 Motorway project, a crucial stretch for EURO 2012, despite low traffic projections and complex negotiations. Discover the unique clearing system between the concessionaires for efficient toll revenue distribution.

jclaborn
Download Presentation

A2 Motorway Project: Overcoming Challenges for EURO 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 43rdASECAP Study & Information Days 2015 The race towards Robert M. Nowak – Autostrada Wielkopolska SA II President Epic Sana Hotel 27-29 May 2015 www.asecapdays.com

  2. Background (2007-2009) • 106 km A2 Motorway- TEN corridor • WithinAWSA Concessioncontract • Higlyrequiredstretch • But lowtrafficprojections • 4 years of negotiations(2004-2008) • UEFA decision re „EURO2012” in 2007 • Differentremunerationschemesproposed by stateadvisors - unbankable

  3. Background (2007-2009) • 106 km A2 Motorway - TEN corridor • Within AWSA Concession contract • Higly required stretch • But low traffic projections • 4 years of negotiations (2004-2008) • UEFA decision re „EURO2012” in 2007 • Different remuneration schemes proposed by state advisors - unbankable

  4. The race towards EURO 2012 • Differencesin approach, many years of ineffectivenegotiations • EURO 2012 on top of the political agenda • 2008 switch from fulltrafficriskintoavailabilityscheme • Negativeimpact of economicturmoilfollowing the LB collapse • 1 moreyear of negotiations to reach the financialclose • Need to set upnew SPV and transfer concessionrights • Necessity to combine open and closedtollingsystems • However…….

  5. Managing the risk despite diversity • Yes, we can……………….. • Lack of timeimprovednegotiations • Politicalcourage of the decisionmakersto revisit the risk profile • Strongsupport from EIB • 3 months of negotations with Lenders – Financial Close June 2009 • Biggesttollmotorwayproject 2009/2011: • ca. 1,5 bilion € overallprojectcost • ca. 1,3 bilion € constructioncostturnkeycontract • ca. 1 bilion € EIB, ca. 0,4 € bilion commercialbanks • ca. 0,2 € bilion junior fundsincluding equity • Commencement of works - July 2009 • Completion of works – November 2011 • Commencement of tolling – May 2012

  6. The power of commitment • Strongdetermination of the concessionaire and beliefin the project • Flexibility of the governmenttowardsslightly different risk profile • Teamsworking to achieve one commongoal • Project executed : • Sixmonthsahead of the tollingcommencementdeadline • Within the budget • No events of bancruptcy of constructionpartners

  7. The only fast clearing system between SPVs in Europe • Unique clearing system allows the immediate distribution of the toll revenue among two concessionaires (AWSA and AWSA II): • No monthly phasing • No mutual set-off • No impact on final user • No double receipts • TransparencytowardsMinistry of Infrastructure

  8. Finally ….. This challenge made them happy……

  9. Finally ….. This challenge made them happy…… 22 June 2012, Gdańsk Ergo Arena Germany 4 : 2 Greece

  10. www.autostrada-a2.pl Thank you Questions please 