An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ePermitting Project Update and Demo January 18th, 2017

  2. Agenda • Scope and Defining Success • Phase 1 Timeline and Activities • Operator Training • Phase 1 Main Features • Future Timeline • Application Demo • Questions

  3. Scope and Defining Success • Stakeholders and Sponsors for this project will be kept informed of progression throughout the lifecycle of the project. • Application design MUST be scalable to quickly phase in other applications. • Internal User/Approvers will have the ability to review submitted documentation • Enhancements will be implemented in a phased approach. • External Users will have the ability to submit the Bituminous Surface Mine application electronically

  4. Project Timeline & Activities • Kick-off – March 30, 2016 • Requirements definition – March 30 thru May 13, 2016 • Development – May 16 thru November 23, 2016 • System testing – November 26, 2016 thru January 6, 2017 • User Acceptance Testing – January 9 thru February 3, 2017 • Training – February 6 thru February 10, 2017 • Production deployment – February 13, 2017

  5. Operator Training • Two live training sessions to be offered. • Feb 6th New Stanton DMO 2:30 – 3:30 PM • Feb 8th Moshannon DMO 2:30 – 3:30 PM • One live webinar training session to be offered. • Feb 10th 10:00 – 11:00 AM • Webinar training will be recorded for those who cannot attend and for future. • Operator guide will be available for download. • Registration information forthcoming

  6. ePermitting Phase 1 Features • Applicants will have the capability to log into Greenport and submit Bituminous Surface Mine applications electronically. • Applicants may submit payment for permit fees via ACH or credit card. • DMOs may review application, create correction notices and return to the applicant for revision. • Outside cooperating agencies may review and make comments electronically. • Public may review and make comments electronically. • Security and CA2 Certification.

  7. Future Timeline • Phase 2 – Feb 2017 thru August 2017 • “Globalize” ePermitting • EFACTS Integration, providing more interactive status updates • Updates to existing application when needed • Additional permit applications

  8. Questions?